Student Q&A

Questions students asked about the study notes, with answers from The Exit Club.

1. Contract Development / Project Planning

K1Architects Practice Act2 questions

Asked by Dana Grayson

Wait so if I'm already a lisenced architect and I help my brother out for free designing a small 1-story woodframe house, do I still have to stamp and sign the plans even though it falls under the licensing excemption? And do I need a writen contract if he's not paying me anything?

The Exit Club

Yep on signing and stamping, and no on the written contract.

Licensing exemptions follow unlicensed people, not the building. They let someone without a license design a conventional woodframe house up to two stories and a basement, but once you're licensed in California, you still sign and stamp plans you prepare for others (K1). Doing it for free for family doesn't turn that off.

You're off the hook legally on the written contract, though. Unpaid work is one of the five exceptions to California's written contract rule (BPC 5536.22). Still smart in real life to jot down the scope with family, just not required on the CSE.

Asked by Manda Wong

What's the difference between gross and ordinary negligence?

The Exit Club

Ordinary negligence is failing to meet the standard of care. Basically, you didn't handle things the way a reasonably careful California architect would have in the same situation. You're only held to what's reasonable, though, so an honest mistake on its own doesn't automatically count as negligence. Gross negligence goes a lot further. That's an extreme departure from the standard of care where you're showing almost no care at all, like if a contractor points out a cracked beam twice and you just brush it off.

On the CSE, this mostly comes up in two spots. When you do volunteer emergency inspections, you're shielded from ordinary negligence claims, but not gross negligence (K1). Same thing with limitation of liability clauses. They can cap what you're on the hook for, but they never cover gross negligence or willful misconduct (K9).

If it helps to keep them straight, I usually think of ordinary negligence as slipping up, and gross negligence as looking the other way.

K9Risk management1 question

Asked by Dana Grayson

Ok sorry if this is a basic question but the claims-made E&O stuff is really confusing me. Say my firm finishes a project in 2026, we switch to a diffrent insurance carrier in 2028, and then in 2030 the owner sues us over a roof leak from that 2026 job. Which insurer actually pays, the 2026 one or the 2028 one? And if switching carriers resets our retroactve date does that mean we're just totally uncovered for every old project we ever did?? Also why can't we name the owner as an additonal insured on E&O when we already do it on general liabilty?

The Exit Club

The 2028 carrier (whichever policy is active in 2030 when the claim is actually made and reported) is the one that pays, not the 2026 one. Claims-made E&O cares about the policy in force when the lawsuit hits, not when you drew the plans (K9).

And yeah, if switching carriers resets your retroactive date to 2028, that 2026 project and anything older really would be uncovered. The old policy is over, and the new one won't look back past 2028. Firms avoid that gap by having the new carrier keep their original retroactive date (prior acts coverage) or buying tail coverage from the old carrier.

For additional insured status, general and auto liability cover third-party injuries or property damage where the owner could get dragged into a suit. E&O covers negligent design services, which the owner isn't doing, and policies exclude insureds suing each other anyway. That's why B101 only adds the owner to general and auto liability, never E&O.

2. Schematic Design / Discretionary Approvals

K16Users & design solutions1 question

Asked by Manda Wong

I thought CA Government Code § 7597 has a 20 ft no-smoking restriction, not 25 ft?

The Exit Club

You're right that Government Code 7597 says 20 feet. That's a different law, though. It covers public buildings, like state or city offices, and keeps smoking 20 feet from a main exit, entrance or operable window. The 25 feet in the lesson comes from CALGreen. Basically, when a nonresidential building has an outdoor smoking area, CALGreen keeps smoking at least 25 feet from building entries, outdoor air intakes and operable windows. Both can apply to the same building, and 25 feet covers both, so that's the one you'd design to.

For the CSE, stick with CALGreen's 25 feet. That's the one in our lessons, here with indoor air quality (K16) and again with the rest of CALGreen (K28).

If it helps to keep them straight, I usually think of the 20 feet as the rule for people lighting up outside a government building, and the 25 feet as the rule for us when we decide where the smoking area goes.

K21CEQA1 question

Asked by Jamel Beltran

Quick question on CEQA. If a private building is basically by-right and only needs a normal building permit, except the owner asks for one small parking varience, does that trigger CEQA for the whole project or just the parking part? Also I keep mixing up statuatory vs catagorical exemptions, which one is the one that has exceptions you have to check first? Thank you!!

The Exit Club

It triggers CEQA for the whole project, not just the parking part. Under CEQA Guidelines 15268(d), a project has to be entirely ministerial to skip CEQA. Even one discretionary approval like a variance pulls the whole project into review (K21). That doesn't automatically mean a full EIR, though, since the project could still qualify for an exemption.

Categorical exemptions are the ones with exceptions you have to check first (like a sensitive location or cumulative impacts). Statutory exemptions come straight from the Legislature, like emergency repairs, so they aren't subject to those exceptions. If it helps, think of statutory as locked in by statute, while categorical is a general class that still needs a quick exception check.

K22California Coastal Act1 question

Asked by Jamel Beltran

If a city already has a certified LCP and approves our CDP, can someone still appeal it to the Coastal Comission on ANY lot in the coastal zone, or only in the appealable areas?

The Exit Club

Only in the appealable areas, not on any lot in the coastal zone. Once a city has a certified LCP, its CDP approval is final for inland lots outside those appeal zones (K22).

Under the Coastal Act (PRC 30603), local permits can be appealed to the Coastal Commission only in specific spots, like between the sea and the first public road, near a wetland, stream, or coastal bluff top, or for major public works and energy projects. Outside those areas, the city's approval stands.

K28CALGreen1 question

Asked by Annagrace Walton

Do we need to memorize every number in the EVCS / EV capable table? I would assume they would provide the chart in a question, but maybe not?

The Exit Club

The question format of the exam doesn't allow for any tables, so having to memorize the EVCS chart falls exactly in the gray zone. It wouldn't be strange if the exam asked you "how many EV spaces for 45 parking spaces?" In fact, that would be a likely question in my opinion.

But whether it's worth your time memorizing the table (rather than just knowing the big numbers) is another issue. Think of it this way. How many candidates who sit for the exam have this memorized? If you think that's less than 20%, then it's probably not worth your time.

It's a test strategy and triage question in the end.

K30California accessibility1 question

Asked by Jamel Beltran

I keep getting tangled up on the 20% path of travel math for tenant improvments. Under the ~$200k valuation threshold 20% is a cap so you go down the priority list and stop once you hit 20%, that makes sense. Over the threshold full compliance is required unless the building offical approves an unresonable hardship, and then you still have to spend at least 20%. Wait, what if full path of travel compliance on a $400k TI only costs like $45k? Obviously the owner doesn't have to spend $80k if everything is already compliant at $45k right? Also does the 3-year lookback count work done by a previous tenant in the same space or only the same owner?

The Exit Club

Yep, you just spend the $45k and you're done! Once the path of travel is fully compliant, there's nothing left to upgrade. That "at least 20%" floor above the threshold only comes up when full compliance is an unreasonable hardship and the building official approves a partial upgrade instead (K30). If full compliance only takes $45k on a $400k TI, you don't even ask for a hardship. You just fix it and move on.

For the 3-year lookback, yeah, work from a previous tenant still counts. Under CBC 11B-202.4 Exception 8, the rule follows the path of travel, not the tenant or owner. So any permitted alterations sharing that same path of travel in the last three years get stacked together against the threshold.

3. Design Development

K35Site hazards1 question

Asked by M. Nguyen

Hello. If we build in a Very High fire zone with stucco, a Class A roof, and 100 ft of defnesible space, can the city downgrade our lot to a Moderate zone?

The Exit Club

Nope, the city can't downgrade it. Fire Hazard Severity Zones map the hazard of the land itself, not the building sitting on it (K35).

Stucco, a Class A roof, ember-resistant vents, and 100 feet of defensible space definitely lower your building's risk, which is the whole point of the WUI rules. They just don't change the mapped zone. When cities adopt CAL FIRE's maps, they can add areas or raise a rating, never lower a state designation.

K37California Energy Code1 question

Asked by Jamel Beltran

On the performace path for Title 24 Part 6, I know you can do trade-offs like better glass to make up for less wall insulaton, but can you trade off mandatory measures too if the whole-building model still beats the energy budget? Also do we actually need to memorize who signs all four NR forms (NRCC, NRCI, NRCA, NRCV) for the exam or is that overkill?

The Exit Club

Nope, you can never trade off mandatory measures. They're the hard floor on both paths (K37). Even if your model crushes the energy budget, you still have to hit every mandatory minimum (equipment efficiency, minimum insulation and air sealing, rated windows, lighting controls, and solar-ready roof area where required). You can only trade off above that floor.

As for the four NR forms, I'd definitely learn them. Unlike a big code table, there are only four, and who signs each one is pretty fair game on the CSE. The easy part is the letters match the timeline and the person doing the work.

NRCC (Compliance) is signed at permit by the author and the responsible architect or engineer. NRCI (Installation) is signed on site by the installer. NRCA (Acceptance) is signed before final by a certified Acceptance Test Technician, and NRCV (Verification) is signed by an independent ECC Rater.

4. Construction Documents / Permitting

K41Working with regulatory agencies1 question

Asked by Manda Wong

Does the DSA review accessibility for hospital projects? I thought that they establish accessibility standards but HCAI enforces them. Are you able to provide the source that states this?

The Exit Club

You're right, and our table had it wrong. DSA writes the accessibility rules, but it doesn't review hospital projects. HCAI does. We fixed the lesson.

Here are the two sources. CBC Section 1.10.1 names OSHPD, which is now HCAI, as the enforcing agency for general acute care hospitals and says it "shall enforce the Division of the State Architect-Access Compliance regulations" for those facilities. HCAI also says it directly in Code Application Notice 2-11B, Accessibility in Health Facilities. That notice explains that DSA-AC adopts the accessibility requirements and OSHPD enforces them for hospitals, skilled nursing facilities, and intermediate care facilities.

On the CSE, this would most likely show up as a question asking who checks accessibility on a hospital project, and the answer is HCAI, not DSA. For most other buildings it's the local building department, and DSA does that review for public schools and community colleges.

5. Project Bidding and Construction

K48Construction change documents1 question

Asked by Manda Wong

DSA's new IR A-6 became effective in November 2026, which I believe eliminates Categories A and B. Do you know if the CSE will reflect this change? What about other updated codes? Will the CSE exam be testing on the 2025 code edition and not the 2022?

The Exit Club

Yep, DSA's new IR A-6 did get rid of the Category A and B labels. We stick to whatever is on CAB's CSE reference list, though, and IR A-6 isn't on it.

For DSA, CAB still links the 2022 Administrative Code (Chapter 4), which still uses Categories A and B. So until CAB updates that link, we're keeping K48 on 2022.

The actual rule didn't really change much anyway. If a change touches structural safety, access compliance, or fire and life safety, you still need DSA approval before starting the work (Category A in K48). Everything else just doesn't go to DSA anymore.

Same deal for the rest of the codes. CAB's reference list already points to the 2025 Building, Energy, CALGreen, Mechanical, Plumbing, Fire, and Wildland-Urban Interface codes, so that's what our notes follow. The 2022 Administrative Code for DSA is the one spot CAB hasn't updated yet.

K50Applications for payment1 question

Asked by Manda Wong

The retention percentage was updated this year for a max of 5% for private projects as well (Civil Code 8811).

The Exit Club

Yeah, you're right, and our K50 table was behind on this one. CAB's reference list links straight to the live Civil Code (sections 8000 to 9566), which now includes Civil Code 8811, so we updated K50 to match.

Basically, for private contracts signed on or after January 1, 2026, retention maxes out at 5% of each payment and 5% of the total contract price, same as public work (K45). That flows down to subs too, and private owners still have 45 days after completion to release it.

There are just two exceptions. Purely residential projects (not mixed-use) that are four stories or less still leave retention up to the contract. And if a sub was told at bid time they needed a performance and payment bond and didn't turn one in, the contractor can hold more from them.

Outside of those two, go with 5% for both private and public work.