K21 — CEQA
CEQA, the California Environmental Quality Act ("SEE-kwa"), is a 1970 state law requiring public agencies to study environmental effects, seek feasible ways to avoid or soften harm, and take public and agency comments before approving a project.
CEQA is a law, not an office with a reception desk. Nobody submits plans "to CEQA." Approving agencies run the review themselves under the CEQA Guidelines. It can add months to a schedule and write mitigation straight into your specs, built around four big ideas: it's a law, one lead agency runs it, three documents sort impacts, and set clocks govern review and lawsuits.
Question
A small project fits a categorical exemption, and none of the exceptions apply. Does it still need an EIR?
When CEQA applies
CEQA triggers when a public agency makes a discretionary decision (using judgment to say no or attach conditions, like a conditional use permit, tentative map, or design review). A ministerial approval checks fixed standards (like most building permits).
- An entirely ministerial project is exempt. One discretionary approval puts the whole project under review.
- Private funding doesn't escape CEQA: privately funded projects needing a discretionary approval still get reviewed.
- Statutory exemptions come from the Legislature (like emergency repairs) and aren't subject to exemption exceptions.
- Categorical exemptions cover project classes (like small additions) that usually lack significant effects, yet have exceptions (like a sensitive location) to clear first.
- For an exempt project, the agency can file a Notice of Exemption (NOE) and stop there.
Environmental effects
CEQA evaluates physical changes: runoff, air, wildlife, traffic, and noise. Effects can be direct, indirect, or cumulative, meaning even a tiny project counts when combined with approved neighbors. "Significant" means a substantial change for the worse.
CEQA and agency roles
One lead agency prepares a single environmental document for the whole project, and other agencies rely on that same document for their own decisions. Each agency still votes on its own permit.
| Role | What it does | Example |
|---|---|---|
| Lead agency | Prepares the document and decides on the project as a whole | Usually the city or county |
| Responsible agency | Holds its own discretionary permit over part of the project using the lead agency's document | Water board or air district issuing a permit |
| Trustee agency | State agency guarding natural resources held in trust | California Department of Fish and Wildlife |
| Commenting agency | Comments without being lead or responsible | Air district with no permit on the project |
The State Clearinghouse, inside the state planning office (the Governor's Office of Land Use and Climate Innovation (LCI), formerly the Office of Planning and Research), distributes CEQA documents whenever a state agency is involved, lengthening minimum review periods.
Question
A mitigation measure is in the approved EIR. Does that prove it actually got done during construction?
Environmental review process
The Initial Study is the lead agency's first look, choosing among three documents: a negative declaration (ND) (no significant effect), a mitigated negative declaration (MND) (agreed fixes pull every effect below significant), or an environmental impact report (EIR).
Whenever substantial evidence supports a fair argument that a significant effect might happen, an EIR is required, even if opposing studies disagree. Nobody has to prove harm will happen. An MND only works when agreed changes clearly neutralize every effect.
An EIR studies the project, significant effects, mitigation measures, and a reasonable range of alternatives, always including the "no project" alternative. For private projects, the lead agency generally gets one year for an EIR and 180 days for an ND or MND once the application is accepted as complete.
The CEQA notices
Four acronyms, four moments. Drill them until they stop blurring together:
| Notice | When it's filed | Where |
|---|---|---|
| Notice of Exemption (NOE) | Project is found exempt | Local agencies: county clerk (plus State Clearinghouse online under current law). State agencies: LCI. |
| Notice of Preparation (NOP) | Lead agency starts an EIR and asks agencies what to cover (scoping) | Sent to responsible, trustee, and federal agencies |
| Notice of Completion (NOC) | Draft EIR opens for review | Filed with the State Clearinghouse |
| Notice of Determination (NOD) | After project approval | Local agencies: county clerk (plus State Clearinghouse online under current law). State agencies: LCI. |
Filing starts a tight lawsuit window: 30 days after an NOD, 35 days after an NOE. CEQA's Notice of Completion has zero connection to the construction Notice of Completion for liens in K46.
Public review and decision
Public review starts once the NOC is filed and public notice goes out for a draft EIR, or at public notice for an ND or MND.
| Document | General review period | Through the State Clearinghouse |
|---|---|---|
| Draft EIR | 30 to 60 days | At least 45 days |
| ND or MND | At least 20 days | 30 days |
Then the decision:
- The lead agency reviews comments, adopts the ND or MND (or certifies the final EIR), and decides on the project.
- Certifying an EIR never approves the project. Certification confirms adequacy, while approval takes separate findings on each significant effect. For unavoidable impacts, the agency can adopt a statement of overriding considerations saying benefits justify them.
- A responsible agency requires mitigation only within its own authority, and each approving agency files its own NOD.
Adopted mitigation is enforced through a mitigation monitoring or reporting program naming who performs and verifies each measure. A grading habitat buffer belongs in the drawings, specs, and contractor duties. Separate coastal, water, and building permits may still follow CEQA.
K21 / Quick check
Quiz
TLDR · Quick Reference
- California Environmental Quality Act (CEQA)
- A 1970 state law, not an agency. Nobody submits plans "to CEQA" because approving agencies run the review themselves.
- Agencies
- The lead agency prepares one document for the whole project. Responsible agencies hold their own permits, trustee agencies guard state resources, and commenting agencies weigh in.
- Exemptions
- Entirely ministerial projects are exempt. Statutory exemptions come from the Legislature, while categorical exemptions cover project classes and require checking exceptions first.
- Three documents
- Negative declaration (ND) for no significant effect, mitigated negative declaration (MND) when agreed changes drop effects below significant, and environmental impact report (EIR) for full study.
- Four notices
- Notice of Exemption (NOE) for exemptions, Notice of Preparation (NOP) to scope an EIR, Notice of Completion (NOC) when the draft EIR drops, and Notice of Determination (NOD) after approval.
- Review periods
- Draft EIR 30–60 days (at least 45 through the State Clearinghouse). ND or MND at least 20 days (30 through the Clearinghouse).
- Separate steps
- Certifying an EIR confirms adequacy. Approving the project and issuing separate permits are distinct steps.
- Timing
- Generally up to one year for an EIR and 180 days for an ND or MND. Filing an NOD starts a 30-day lawsuit clock (35 days after an NOE).
Student Q&A
Questions students asked about K21, with answers from The Exit Club. All questions
Loading questions…
Something in K21 unclear? Log in to ask a question.
Log in to askYour questions
Sources & handbook wording
K21 · Knowledge of methods and procedures for complying with California Environmental Quality Act (CEQA) as it relates to design and construction.
- CAB CSE Handbook, April 2026 ↗
PDF p.13, K21. Official scope only
- CEQA Guidelines: Title 14, Division 6, Chapter 3 ↗
§§15050–15053, 15060–15075, 15082–15097, 15105. CAB-named work, official text endpoint. §15268(d), project with both ministerial and discretionary elements. §§15091,15093,15126.6: findings, overriding considerations and alternatives
- LCI: Environmental document submission: supplemental primary source ↗
Current NOD/NOE filing: local NODs and NOEs to county clerk and LCI (State Clearinghouse). SB 69 effective January 1, 2024 · Supplemental clarification of current notice filing. Not a separate CAB-listed exam reference.