K33 — Integrating building systems
Structure, ducts, and conduits claim real square footage, real ceiling depth, and real maintenance access, meaning building systems shape your floor plan long before the first utility bill arrives. Coordination is keeping their space, structural support, and service clearances from colliding. One extra incentive to love this section: Design Development is 15 percent of the exam packed into just five chapters (roughly 3 percent per chapter, compared to under 2 percent almost everywhere else), giving these five chapters the highest point-per-page return in the syllabus.
What each design phase produces
| Phase | What it produces |
|---|---|
| Schematic design (SD) | Conceptual site plan, preliminary plans, sections, and elevations, a narrative of major materials and systems, maybe an outline spec, and a cost estimate |
| Design development (DD) | Developed plans, sections, and elevations, typical construction details, and an updated outline spec and estimate |
| Construction documents (CDs) | Coordinated contract drawings and the project manual (specs, conditions, bidding instructions), plus an updated estimate |
Systems and approvals
Because entitlement review usually lands during DD, agency comments can still nudge the footprint. Pin down what moves walls and slabs early, and hold detailed sizing until approvals clear (K42 maps the full sequence).
| System | During DD and entitlement | During construction documents |
|---|---|---|
| Structure | General system worked out | Fully designed |
| Exits, stairs, elevators | Locations set | Details finished |
| Mechanical, electrical, and plumbing (MEP) | Selected in general terms | Selected and fully designed |
Exits, stairs, and elevators lock down early because they carve pits, shafts, headroom, structure, and power through every floor. Detailed MEP waits until entitlement settles so one planning setback doesn't turn weeks of equipment sizing into recycling-bin fodder.
Select and coordinate systems
Every system demands space, support, and service access. Whenever a duct slams into a beam or a gravity drain loses its fall over a girder, pull the consultants into one room and solve it on paper rather than punting it to the jobsite. If thermal loads climb after design starts, the mechanical engineer recalculates and proposes changes: the architect never casually upsizes ducts, and the contractor never resizes equipment in the field.
Plumbing and electrical basics
- Water supply: hand the plumbing engineer an accurate fixture count in SD and flag every change. Each fixture carries a water supply fixture unit (WSFU) weight, and large buildings size pipes by probability because nobody coordinates every flush at once.
- Drain, waste, and vent (DWV): drains rely on gravity. Traps hold water seals that block sewer gas, and vents let air in so drains actually flow.
- Electrical service: power travels from utility to meter to main panel, with larger buildings needing transformers and dedicated electrical rooms. Plumbing and electricity are mandatory, while gas is optional.
- 2025 Energy Code electrical loads: on the prescriptive path, single-zone systems in offices, retail, and schools start from a heat pump baseline, and new offices, retail, schools, warehouses, hotels, and restaurants add solar panels plus battery storage. Size your electrical service and roof space for both from day one (K37).
Plumbing Code fixture counts
California Plumbing Code (Title 24, Part 5) governs minimum fixture counts:
- Sizing the count: pull the occupant load from the building code, split it 50 percent male and 50 percent female, apply the occupancy fixture table, and round fractions up. Re-run the math whenever a change of occupancy adds occupants.
- Separate facilities: men's and women's restrooms are the default, except when total occupant load is 10 or less, or in a business or mercantile occupancy with 50 or less total occupants (one single-user toilet serves everyone). All-gender multi-user restrooms with lockable privacy compartments work too, and single-user rooms carry all-gender signage.
- Water closet parity: female water closets must at least equal male water closets plus urinals.
- Drinking fountains and service sinks: drinking fountains never go inside toilet rooms, and most nonresidential occupancies require one service sink.
- Flow limits: match the California Green Building Standards Code (CALGreen) caps in K28.
Mechanical Code ventilation and exhaust
California Mechanical Code (Title 24, Part 4) covers ventilation and exhaust:
- Outdoor air: calculated as a rate per person plus a rate per square foot, never flat air changes. Wherever the Energy Code applies, Energy Code ventilation rules govern over the Mechanical Code (which is why CALGreen points straight to the Energy Code).
- Exhaust and clearances: public restrooms exhaust per toilet or urinal, and enclosed parking garages require mechanical exhaust unless open on two or more sides.
- Commercial kitchen hoods: a Type I hood captures grease and smoke (fryers, grills, broilers), while a Type II hood handles steam, heat, and odors (dishwashers, steamers).
HVAC system selection
Heating, ventilation, and air conditioning (HVAC) design begins with zoning spaces that behave differently (sun-baked perimeter offices versus interior conference rooms). Next pick central (quieter, more efficient, longer life, easier maintenance, hungrier for duct space) or local (compact, individual control, lower upfront cost, noisier, shorter lifespan).
| System | Fits | Catch |
|---|---|---|
| Variable air volume (VAV) | Large multi-zone buildings | Needs reheat to warm one zone while cooling another |
| Constant air volume (CAV) | Big open floors with even loads (department stores) | Runs as a single zone |
| Fan-coil units | Hotels, apartments, and offices where every room has an exterior wall | Weak humidity control, requires condensate drains |
| Closed-loop heat pumps | Buildings where one zone overheats while another needs heat | Transfers heat between zones |
| Hydronic radiant | High ceilings and heavy air leakage (loading docks) | Needs separate ventilation |
In hot, dry climates, evaporative coolers sip electricity, yet they only cool and stop working once humidity climbs.
Question
The replacement rooftop unit has the same cooling capacity but it's heavier and needs more power. Can it be swapped in without other checks?
Special structural loads
Heavy equipment, compact mobile shelving, or free-weight gym racks add dead load and concentrated loads. Give the structural engineer real equipment data so they can size deeper beams and joists, closer spacing, closer columns, or a mix.
Watch the classic gym trap: loaded weight racks on the second floor of a wood-framed building need deeper joists and closer posts, and extra posts drop straight into the floor plan downstairs, meaning the owner must hear about it early.
Never wave through a substitute rooftop unit on cooling tonnage alone: if it weighs more or draws more power, check structure, electrical, roof openings, controls, and access first.
Energy management
Passive design cuts heating and cooling loads before you buy a single piece of equipment, making it the first move on any tight-budget green building:
- Passive moves: solar orientation, daylighting, natural ventilation, and south overhangs that block high summer sun while welcoming low winter sun.
- Lighting: light-emitting diodes (LEDs), multilevel and daylight controls, and occupancy sensors.
- Mechanical: right-sized gear and zoned controls. Conditioning recirculated air never supplies code-required outdoor air (ductless split heat pumps still need a dedicated fresh-air path).
- Thermal comfort: temperature, humidity, air movement, and radiant temperature working together. Exhaust moisture directly from kitchens, laundries, restrooms, and locker rooms.
- Envelope: continuous insulation and tight air sealing. On residential projects, an independent Energy Code Compliance (ECC) Rater field-verifies much of that work (K37, K34).
Keep energy and water systems in separate buckets: photovoltaics make electricity, solar thermal heats water, and ground-source heat pumps exchange heat with the earth, whereas graywater and rainwater save water (never the right answer to an energy question).
Energy-management controls
An energy management system (EMS) or building automation system (BAS) runs on a continuous feedback loop: sensors report temperature, humidity, carbon dioxide (CO2), and occupancy to the controller, the controller compares readings against setpoints and adjusts equipment, and the cycle measures again. The controller is always what decides the response.
Question
The survey shows a water main right next to the site. Is water service for the building confirmed?
Site utilities
The client hires a licensed surveyor whose site survey maps existing utility lines. Review it early because utility availability and extension costs can relocate the entire building.
- Water: fire sprinklers demand real flow and pressure, requiring actual flow-test data on the main.
- Sanitary sewer: gravity drains need downhill fall, making the main's invert elevation the hard floor for gravity plumbing (basement drains below the main require a pump). No municipal sewer means an engineered septic tank and leach field, which demands both land area and draining soil.
- Electric and gas: confirm capacity and transformer placement early (many new California buildings skip gas completely).
Keep four similar-sounding stormwater tools straight:
- Bioswale: vegetated channel conveying and treating runoff
- Bioretention area (rain garden): planted basin collecting, filtering, and soaking in runoff
- Retention basin (wet pond): holds water permanently
- Detention basin (dry pond): holds runoff temporarily and releases it slowly
The civil engineer lays out site utilities while electrical, plumbing, and fire protection consultants take over about 5 feet from the building (lock down exact handoff points). Gravity sewers and storm drains claim the right of way first because pressurized pipes and conduit can dodge them.
Utilities and serviceability
Serviceability means crews can install, maintain, and eventually replace every machine: verify the delivery path, working clearances, coil pull space, and how a dead unit leaves the building twenty years from now.
- Verify before designing: a pipe or wire on a survey is only a rumor until the utility confirms capacity, connection, and timing (often via a written will-serve letter). Build long transformer upgrade lead times directly into the schedule.
- Vibration isolation and seismic restraint must work together.
- Any equipment added after the load schedule goes out loops straight back to the consultants.
K33 / Quick check
Quiz
TLDR · Quick Reference
- Phase outputs
- Schematic design (SD) delivers concept drawings, a systems narrative, and an estimate. Design development (DD) adds typical details. Construction documents (CDs) deliver coordinated drawings and the project manual.
- Timing
- Locate structure, exits, stairs, and elevators in DD. Keep mechanical, electrical, and plumbing (MEP) general until entitlement settles the footprint.
- Site utilities
- A street line isn't confirmed service until the utility verifies capacity. Civil handles site utilities, building trades take over about 5 feet out, and sewer invert elevation limits gravity drains.
- Heating, ventilation, and air conditioning (HVAC)
- Zone first, then choose central or local. Variable air volume (VAV) fits multi-zone buildings, constant air volume (CAV) big open floors, fan-coil units exterior-wall rooms.
- Loads
- Heavy gear and compact shelving create concentrated loads (deeper or closer framing, closer columns). Growing thermal loads return to the mechanical engineer to recalculate.
- Plumbing Code
- Size fixtures from the occupancy table (50/50 male/female, round up). Separate rooms required unless 10 or fewer occupants, or business/mercantile with 50 or fewer.
- Mechanical Code
- Outdoor air is per person plus per square foot (Energy Code ventilation governs where applicable). Type I hoods catch grease and smoke, Type II catch steam and heat.
- Passive first and controls
- Orientation, overhangs, daylight, and a tight envelope cut loads before equipment starts. In an energy management system (EMS), sensors measure and the controller decides.
Student Q&A
Questions students asked about K33, with answers from The Exit Club. All questions
Loading questions…
Something in K33 unclear? Log in to ask a question.
Log in to askYour questions
Sources & handbook wording
K33 · Knowledge of methods and procedures for evaluating and integrating building systems and utilities into the project design.
- AIA B101–2017: Owner–Architect Agreement ↗
Sections 3.1.2, 3.1.5, 3.2.5, 3.3 and 3.4. Local sample PDF pp. 6–8 · Contractual framework. Applies when this agreement is used, as amended.
- 2025 California Building Code ↗
Chapter 16, Structural Design. Chapter 17, Special Inspections and Tests · Use the adopted edition and project-specific structural criteria.
- CAB CSE Handbook, April 2026 ↗
K33 scope statement only. Detailed technical requirements supported separately
- CBC 2025 Chapter 16 ↗
Structural and nonstructural design loads. Adopted referenced standard
- 2025 California Mechanical Code: Ventilation ↗
Chapter 4. Ventilation requirements
- 2025 California Mechanical Code: Exhaust Systems ↗
Chapter 5. Exhaust systems, including commercial kitchens
- 2025 California Plumbing Code: Plumbing Fixtures ↗
Chapter 4. Plumbing fixtures and fixture fittings