K46 — Liens & payment protection
California gives unpaid workers, suppliers, and design professionals two distinct hooks to collect what they're owed: a lien attaches to the real estate, while a stop payment notice freezes the construction funds. That split matters enormously because you can't slap a mechanics lien on public property (nobody gets to foreclose on a public high school).
| Remedy | Where it applies |
|---|---|
| Design professional lien | Private project where construction hasn't started yet |
| Mechanics lien | Unpaid work or materials on private property |
| Stop payment notice (or stop notice) | Construction funds on private or public projects |
Question
The owner hasn’t paid the architect. The permit has been issued, but construction hasn’t started. Can the architect record a design professional lien?
Design-professional lien
Licensed architects, landscape architects, registered engineers, and land surveyors can lien private property for unpaid design fees when a project stalls before groundbreaking. It fills the exact gap where a mechanics lien can't reach, because a shelved set of drawings leaves no work on the dirt.
| Step | What it takes |
|---|---|
| 1. No dirt turned yet | Works only before construction starts (once digging begins, switch to a mechanics lien). Unavailable on an owner-occupied single-family home under $100,000. |
| 2. Government approval | A building permit or other government approval based on your design |
| 3. Demand | Written payment demand sent at least 10 days before recording |
| 4. Record | File with the county recorder within 90 days of knowing construction won't start |
| 5. Enforce | File a lawsuit within 90 days after recording, or the lien expires |
- Private projects only. Public property can't be liened, no matter who tells you otherwise.
- The moment construction begins, a design lien expires and your remedy becomes a mechanics lien.
Mechanics lien
A mechanics lien puts a claim on private real property that can end in a foreclosure sale, and anyone supplying labor, materials, or design work gets lien rights. Here's the twist that ruins an owner's afternoon: an owner who paid the general contractor (GC) every penny can still face a lien from an unpaid sub. That's why smart owners collect signed lien releases, not just friendly receipts.
Preliminary notice
The preliminary notice (or 20-day notice) isn't an accusation, just an introduction telling the owner who holds potential lien rights. It gets served, never recorded.
- Served within 20 days of first furnishing work, it protects the entire job. Served late, it reaches back only 20 days before service. First delivery March 1 with a May 15 notice starts coverage on April 25.
- The GC and an owner-hired architect contract directly with the owner, so they skip sending one to the owner (though they may still owe one to the construction lender).
- Getting a preliminary notice doesn't mean anything went wrong. The owner files it away, and the architect makes sure that sub's lien releases ride along with later pay applications.
Serve, record, enforce
- Serve the owner with the Notice of Mechanics Lien.
- Record the lien with the county recorder within 90 days after completion, or within 60 days (direct contractor) / 30 days (everyone else) if the owner recorded a valid notice of completion or cessation.
- Enforce it by filing a foreclosure lawsuit within 90 days after recording, or the lien expires automatically.
What counts as completion
That 90-day clock starts at completion: actual completion, owner occupancy or use after labor stops, or a long stretch with no labor on site. When labor stops, the owner can also record a notice of cessation.
A notice of completion only shortens lien deadlines if the owner records it within 15 days after completion. Record it on day 50 and it shrinks nothing. Recording belongs to the owner, never the architect (K51).
Recording and enforcement periods
Every deadline is married to its starting gun. Remembering "90 days" without knowing "90 days from what?" is half an answer and zero points.
| Clock | Starts at | Length |
|---|---|---|
| Preliminary notice | First furnishing work | 20 days |
| Design lien recording | Knowing construction won't start | 90 days |
| Mechanics lien recording, no notice | Completion | 90 days |
| Mechanics lien recording, notice recorded | Recording the notice of completion or cessation | 60 days (direct contractor), 30 days (others) |
| Notice of completion | Completion | Owner records within 15 days |
| Foreclosure lawsuit | Recording the lien | 90 days |
Stop payment notice
- Works on both private and public jobs: serve it on whoever holds the money, meaning the owner or construction lender on private work and the public agency on public work.
- Attach a bond to a stop payment notice on a private lender, and the lender must withhold the funds.
Public works
No liens exist on public work, leaving two remedies: a stop payment notice or a claim on the payment bond. Every direct contractor on a public contract over $25,000 must furnish a payment bond before starting work.
Notice of nonresponsibility
A landlord shields its building from liens for tenant-ordered remodels by doing both steps: post a notice of nonresponsibility on site and record it within 10 days of learning about the work. Skip either step and it fails, and an owner who ordered or participated in the work can't use it at all.
Question
A mechanics lien got recorded on time. Can the claimant take as long as they want to file the lawsuit?
Owner payment protection
- Performance and payment bonds, such as American Institute of Architects (AIA) A312 (a bid bond doesn't belong here because it only catches a low bidder who refuses to sign)
- Signed lien releases from subs and suppliers alongside every payment
- Timely payment-application review by the architect
- Retainage, held by the owner, never the architect
- A timely recorded notice of completion to compress the lien window
- The contractor's G706A (Contractor's Affidavit of Release of Liens) at closeout
Lien releases come in progress and final flavors, each conditional or unconditional. A conditional release activates only once payment clears, while an unconditional release means cash is already in hand. Nobody can waive lien rights in advance.
What the architect does
You don't record liens, file the owner's notices, or play lawyer. Your lane is keeping the payment paperwork moving cleanly:
- Unpaid sub calling on a public school? Point them toward a stop payment notice or the payment bond.
- Owner asking you to record the notice of completion? Hand it right back as the owner's filing and advise recording within 15 days of completion.
K46 / Quick check
Quiz
TLDR · Quick Reference
- Lien vs. stop payment notice
- A lien grabs the property, while a stop payment notice grabs the construction money.
- Public works
- No mechanics liens on public property. Claimants use a stop payment notice or the payment bond (required on contracts over $25,000).
- Design lien
- Private job, government approval issued, no construction yet. Demand 10 days before recording, record within 90 days, sue within 90 days.
- Design lien limits
- Unavailable on an owner-occupied single-family home under $100,000, and it ends the moment construction starts (switch to a mechanics lien).
- Preliminary notice
- Served within 20 days of first furnishing, it covers everything. Served late, it reaches back only 20 days before service.
- Recording
- 90 days after completion, or 60 days (direct contractor) / 30 days (everyone else) after a valid notice of completion recorded within 15 days of completion.
- Enforcing
- File a foreclosure lawsuit within 90 days of recording, or the lien vanishes.
- Owner tools
- Performance and payment bonds, lien releases with every draw, retainage, a notice of completion, American Institute of Architects (AIA) G706A, and a notice of nonresponsibility (post and record within 10 days) for tenant work.
Student Q&A
Questions students asked about K46, with answers from The Exit Club. All questions
Loading questions…
Something in K46 unclear? Log in to ask a question.
Log in to askYour questions
Sources & handbook wording
K46 · Knowledge of California laws related to liens and implications for architect and client responsibilities.
- California Civil Code: Works of Improvement ↗
Private-work design-professional/mechanics liens, preliminary notice (§8204), completion (§8180), notice of completion (§§8182, 8190), recording (§§8412, 8414), stop payment notices. Public works: stop payment notice timing (§9356) and payment bonds (§9550) · CAB expressly lists Division 4, Part 6. Statutory remedies and applicable conditions. Not a complete filing manual.
- Civil Code §8444: Notice of nonresponsibility ↗
Owner eligibility. Both posting and recordation within 10 days
- AIA A201–2017 ↗
Payment documentation, retainage, and final lien-release evidence
- CSE Candidate Handbook ↗
Published content outline, Project Bidding and Construction, K46. April 2026 handbook PDF p.16 · Official knowledge-statement scope only. Technical notes also draw on the itemized references.
- Supplemental primary source: Design professionals lien ↗
Civil Code §§8300–8319: private-work eligibility, 10-day demand, 90-day recording and enforcement, and 30-day conversion to a mechanics lien.
- Supplemental primary source: AIA G706A–1994 ↗
Contractor’s Affidavit of Release of Liens. Supporting lien-release documents
- Supplemental primary source: AIA A312–2010 ↗
Performance Bond and Payment Bond. Different claims, notice procedures and surety duties


