K14 — Project scheduling

Knowledge of methods for project scheduling in all phases of projects.

A project schedule puts tasks in sequence and exposes what's waiting on what. Split the calendar right down the middle: the architect schedules professional design services, and the contractor schedules construction.

Contingency and work plan

A schedule contingency is buffer time planned upfront for surprises, like 2 to 4 months on an 8-month job. Contingency is planned, while float is calculated from the network.

For long-lead equipment like custom switchgear, schedule product selection and submittal review before fabrication.