K5 — Contract types

K5 is the AIA field guide: who signs which contract, what it covers, and which form moves a project along. Nail the letter and the signer on each one, and most questions practically grade themselves.

Main agreements

The California Architects Board (CAB) puts four 2017 American Institute of Architects (AIA) documents on its reference list. Know these cold:

Document Who signs it What it does
A101–2017 Owner–Contractor, Stipulated Sum Owner and contractor Sets the Work, Contract Sum, Contract Time, and payment terms, leaning on A201 for everything else.
A201–2017 General Conditions of the Contract for Construction Part of the owner–contractor contract The construction rulebook spelling out owner, contractor, and architect duties.
B101–2017 Owner–Architect Agreement Owner and architect Business terms plus a built-in scope of basic services.
B102–2017 Owner–Architect, without a Predefined Scope Owner and architect Business terms only, waiting for a separate scope document.

Study them in this order: A201, B101, B102, then A101. A201 deserves the spotlight because half the construction questions ask "whose job is this?" and A201 holds the answer key.

One trap catches almost everyone once: A201 doesn't hire the architect. It sits inside the owner–contractor contract and describes your role during construction, meaning you still need your own signed owner–architect agreement.

B101 versus B102

B101 is the ready-to-cook meal: business terms plus basic services from schematic design, design development, and construction documents through bidding and construction administration.

B102 gives you the kitchen with no scope inside, so it only works once you attach a scope document. Its usual partners aren't on CAB's list, so just know what each one does:

B101 comes complete. B102 needs a scope documentB101 is one document containing both the agreement terms and a scope of basic services for schematic design, design development, construction documents, bidding and construction administration. B102 contains only the terms, with no scope of its own. It is paired with a scope document: B201 for design and construction administration, B202 for programming, or B203 for site evaluation and project feasibility.B101 comes complete. B102 needs a scope.One documentB101TermsBasic servicesSD · DD · CD · Bid · CATwo documentsB102TermsNo scopeof its ownB201Design + CAB202ProgrammingB203Site evaluationB102 keeps the same business terms, and you attach whichever scope fits the job.B101 comes complete. B102 needs a scope documentB101 is one document containing both the agreement terms and a scope of basic services for schematic design, design development, construction documents, bidding and construction administration. B102 contains only the terms, with no scope of its own. It is paired with a scope document: B201 for design and construction administration, B202 for programming, or B203 for site evaluation and project feasibility.B101 comes complete.B102 needs a scope.B101TermsBasic servicesSD · DD · CD · Bid · CAB102TermsNo scope of its ownB201Design + CAB202ProgrammingB203Site evaluationB102 keeps the same terms, and youattach whichever scope fits the job.
  • B201: design and construction administration (essentially B101 split into two pieces)
  • B202: programming, before design begins
  • B203: site evaluation and feasibility

Basic, supplemental and additional services

Scope questions almost always come down to which of three buckets a task belongs in:

Group What it is How it works
Basic services The standard design and construction phases Covered by the basic fee
Supplemental services A menu picked at contract signing (programming, interior design, commissioning) Assigned to architect, owner, or nobody. Unassigned means not provided.
Additional services Surprise work popping up after signing (owner-driven redesigns, extra drawings) Get the owner's written authorization before starting

Suppose the owner asks for record drawings that aren't in the agreement. Call it an additional service and get written authorization before lifting a pen. Doing it quietly and billing later, or doing it "as a favor," are the two textbook wrong answers.

Because B101 assumes the owner walks in with a program ready for schematic design, writing the program isn't a basic service.

California add-ons

AIA forms are national, which means a California contract still has to satisfy the Practice Act's written contract rule (K1). B101 covers seven of the eight required items and misses the California add-on: the statement that architects are licensed and regulated by the California Architects Board, plus CAB's address, tucked into special terms. A bare B102 also flunks the rule until its scope document is attached, because a contract with no service description isn't compliant either.

Contract relationships

Two contracts, one projectIn design-bid-build the owner has two separate agreements: B101 with the architect and A101 with A201 with the contractor. There is no contract between the architect and the contractor. They coordinate through the owner’s two agreements.Two contracts, one projectDesign-bid-buildOwnerB101A101 + A201ArchitectDesigns and administersContractorBuilds, controls methodsNo architect–contractor contractThey coordinate through the owner’s two agreements.Two contracts, one projectIn design-bid-build the owner has two separate agreements: B101 with the architect and A101 with A201 with the contractor. There is no contract between the architect and the contractor. They coordinate through the owner’s two agreements.Two contracts,one projectDesign-bid-buildOwnerB101A101/A201ArchitectContractorNo architect–contractorcontractThey coordinate throughthe owner’s agreements.

In design-bid-build, the owner signs two separate deals: one with the architect (B101) and one with the contractor (A101 plus A201). The contractor owns means, methods, and jobsite safety, and the architect and contractor have no contract with each other.

A construction manager as adviser (CMa) coaches the owner without building anything, while a CM at risk takes on construction and holds the trade subcontracts.

Reading an AIA document number

One letter decodes the whole catalog: A is owner–contractor, B is owner–architect, C is everything else (mostly architect–consultant), and G is administration forms. The four digits after the dash are the edition year.

Question

The owner wants a short agreement and plans to write up the services in a separate document. Is B102 made for that?

Other service documents

Architects hire consultants on C401, passing the prime agreement's duties down to each consultant for its slice of the work. It's off CAB's list and covered in K7.

Project delivery, payment and scheduling

Questions love blending these three completely independent dials together:

  • Delivery method decides who designs, who builds, and who contracts with whom (design-bid-build, design-build, CM at risk).
  • Compensation method decides how money changes hands (stipulated sum, cost plus a fee, hourly).
  • Scheduling decides whether phases line up neatly or overlap (fast track).

You can mix and match freely: a single job can be design-build, stipulated sum, and fast tracked all at once (K44).

Compensation Fits when
Stipulated sum (fixed fee) Scope is crystal clear, like a prototype your firm has built ten times
Hourly, often with a not-to-exceed cap Scope is murky, like a 1920s remodel hiding surprises behind every plaster wall
Percentage of construction cost Traditional, though owners tend to notice when your fee climbs with construction prices
Cost plus a fee Mostly for contractors when the work can't be priced upfront

On cost plus a fixed fee, the fee stays frozen even if construction costs move: $920,000 of allowable cost plus an $80,000 fixed fee equals $1,000,000.

Construction forms

Form What it records
G701 Change Order An agreed change to Work, Contract Sum, or Contract Time, signed by owner, architect, and contractor
G702 Application and Certificate for Payment The contractor's pay request and the architect's certification
G703 Continuation Sheet Line-by-line schedule of values, completed work, stored materials, and retainage
G704 Certificate of Substantial Completion The completion date and who owns maintenance, utilities, and insurance afterward
G710 Architect's Supplemental Instructions A minor change with no change to Sum or Time
G714 Construction Change Directive A change ordered before everyone agrees on cost or time

Sort the three change forms by agreement and impact: everyone agrees → G701, work moves before agreement → G714, zero shift to money or time → G710.

Finally, keep pre-contract and day-to-day paperwork straight: an addendum modifies bidding documents before the contract is signed and goes to every bidder. During construction, a request for information (RFI) asks a question and a submittal shows how the contractor plans to comply, and neither one ever changes the Work, price, or schedule. See K47 for the full change playbook.

K5 / Quick check

Quiz

14 questions
← Quiz list
Question 1 of 14Choose one answer
Which American Institute of Architects (AIA) document sets out the duties of the owner, the contractor and the architect during construction?

TLDR  ·  Quick Reference

CAB's list
The California Architects Board (CAB) lists four 2017 American Institute of Architects (AIA) documents: A101, A201, B101, and B102.
A201
The General Conditions rulebook for construction. It lives inside the owner–contractor contract and never hires the architect.
B101 vs. B102
B101 pairs business terms with built-in basic services. B102 has business terms only and needs a scope attached, such as B201.
Supplemental vs. additional services
Supplemental services are chosen at signing. Additional services appear later and need written authorization before work begins.
California add-on
Add the CAB licensing notice (12-point type, with CAB's address) to any AIA owner–architect agreement.
Compensation
Stipulated sum fits a clear scope, hourly fits a murky one, and a fixed fee on cost-plus stays put even if construction costs climb.
G forms
G701 agreed change order, G714 change directive before agreement, G710 minor change with no cost or time shift, G702/G703 payment, G704 substantial completion.
Request for information (RFI) / submittal
An RFI asks a question, a submittal shows how the contractor plans to comply, and neither changes the contract.

Student Q&A

Questions students asked about K5, with answers from The Exit Club. All questions

Loading questions…

Sources & handbook wording

K5 · Knowledge of types of contracts and their application to scope of work and project service requirements.

  1. AIA B101–2017 ↗

    Articles 1–4. §5.13

  2. AIA B102–2017 instructions ↗

    Scope configuration and incorporated service documents

  3. CAB reference materials ↗

    A101, A201, B101 and B102, 2017 editions

  4. Supplemental primary source: AIA B202–2020 programming scope ↗

    Programming scope. Relationship to B102

  5. AIA A201–2017 ↗

    Insurance and bonds. Duties under the construction contract

  6. AIA A101–2017 ↗

    Stipulated-sum agreement and Exhibit A: Insurance and Bonds

  7. Supplemental primary source: AIA C401–2017 ↗

    Consultant scope, responsibilities and relationship to the prime agreement

  8. Supplemental primary source: AIA B201–2017 ↗

    Design and construction contract administration services. Use with B102

  9. Supplemental primary source: AIA B203–2017 ↗

    Site evaluation and project feasibility services

  10. Supplemental primary source: AIA G701–2017 ↗

    Change Order. Agreed changes to the Work, Contract Sum and Contract Time

  11. Supplemental primary source: AIA G702–1992 ↗

    Application and Certificate for Payment. Retainage, previous certificates and current payment

  12. Supplemental primary source: AIA G703–1992 ↗

    Continuation Sheet. Schedule of values, completed work and stored materials

  13. Supplemental primary source: AIA G704–2017 ↗

    Certificate of Substantial Completion. Date, remaining work and assigned responsibilities

  14. Supplemental primary source: AIA G710–2017 ↗

    Architect’s Supplemental Instructions. Minor changes without a Contract Sum or Contract Time adjustment

  15. Supplemental primary source: AIA G714–2017 ↗

    Construction Change Directive. Directed changes before full agreement on adjustments