K56 — Observation, submittals & RFIs

Under American Institute of Architects (AIA) A201, a submittal shows how the contractor plans to meet the contract, and your job is checking that plan against the design concept. Hold that dividing line tight: the contractor builds and owns jobsite safety, while you observe periodically, clarify conflicts, and review for design conformance. Neither a submittal nor a request for information ever quietly rewrites the contract.

Submittal review

The route a submittal takesA subcontractor or vendor prepares the submittal. The general contractor reviews, coordinates and approves it, then sends it to the architect, who reviews it for conformance with the design. It goes back to the contractor marked approved, revise and resubmit, or rejected. The architect’s review doesn’t cover field dimensions, quantities or construction methods, and deviations have to be called out.The route a submittal takes1Sub or vendorPrepares thesubmittal2GeneralcontractorReviews,coordinates,approves3ArchitectReviews fordesignconformance4Back tocontractorApproved,revise andresubmit, orrejectedThe contractor’s review comes first. The architect’s review doesn’t coverfield dimensions, quantities or construction methods.Deviations have to be called out, not tucked into the package.The route a submittal takesA subcontractor or vendor prepares the submittal. The general contractor reviews, coordinates and approves it, then sends it to the architect, who reviews it for conformance with the design. It goes back to the contractor marked approved, revise and resubmit, or rejected. The architect’s review doesn’t cover field dimensions, quantities or construction methods, and deviations have to be called out.The route asubmittal takes1Sub or vendorPrepares the submittal2General contractorReviews, coordinates, approves3ArchitectReviews for design conformance4Back to contractorApproved, resubmit or rejectedThe contractor reviews first. Thearchitect doesn’t check fielddimensions, quantities or methods.Deviations have to be called out,not tucked into the package.
Type What it is
Shop drawings Project-specific drawings, diagrams, and schedules, like fabrication details
Product data Manufacturer illustrations, performance charts, and brochures
Samples Physical examples setting the benchmark the work is judged by
  • Submittals aren't Contract Documents, and reviewing them never changes the contract.
  • Packages follow the chain: sub or vendor → general contractor → architect. Any vendor package skipping the contractor goes back to the contractor unreviewed, even if the contractor was copied.
  • By submitting, the contractor certifies it reviewed and approved the submittal, checked materials and field measurements, and coordinated it.
  • You review for conformance with the design concept. Field measurements, quantities, and construction methods stay the contractor's job, though obvious conflicts still get flagged. Headline capacity isn't the whole check either: power, supports, controls, and code ratings count too.
  • Contractors must flag deviations. An unflagged deviation isn't approved just because your stamp landed on the package. Departures still require a minor change, change order, or Construction Change Directive (CCD).
  • Resubmittals must flag any changes beyond the ones you asked for.
  • Work needing a submittal waits until the architect has acted on it.

Submittal schedule and review actions

  • Review follows the contractor's submittal schedule, or proceeds with reasonable promptness without one.
  • Typical actions: no exceptions taken, make corrections noted, revise and resubmit, and rejected.
  • Unrequested submittals can be returned without action.
  • Under B101, reviewing submittals out of sequence or past the contract limit is an additional service.

Delegated design submittals

For delegated design (like curtain wall anchors or metal stairs), the owner and architect set performance criteria, and the contractor's engineer designs and seals the submittal. You review for design conformance and fit with the building, relying on the specialist's calculations.

Question

The architect sees a crew working in an unshored trench. Does A201 give the architect the power to stop the work?

Limits of the architect’s role

Under A201, you aren't responsible for exhaustive or continuous inspections, contractor means, methods, or jobsite safety, contractor noncompliance, or directing crews.

The architect cannot stop work under the standard contract. Only the owner (unfixed nonconforming work), an unpaid contractor, and the building official (stop work order) hold that brake (K10).

Spot an active life-safety hazard on site (like an unshored trench or unguarded roof edge)? Warn the people there right away and notify the contractor and owner. Speaking up never transfers safety liability to you.

Construction observation

The architect visits the site at appropriate intervals, checks whether observed work conforms, and reports to the owner.

Covered or nonconforming work

  • Against a requirement or request: If the contractor covers work despite an express contract rule or your prior request, on your written request the contractor uncovers and restores it at its own cost, with no extra time. That holds even if the work turns out fine.
  • Properly covered: With no prior rule or request, uncovering on written request splits cleanly: conforming work earns a price and time adjustment, while nonconforming work lands on the contractor.
Who pays to uncover the work?If work was covered against an express requirement or the architect’s request, the contractor pays to uncover and replace it, even if the work is fine. If not, it depends on whether the work conforms. If it conforms, the owner pays through a price and time adjustment. If it doesn’t, the contractor pays to fix it.Who pays to uncover the work?Covered against a requirement or request?YesNoContractor paysto uncover and replace it,even if the work is fineDoes the work conform?YesNoOwner paysPrice and timeadjustmentContractorpays to fixWhy it was covered decides who pays.Who pays to uncover the work?If work was covered against an express requirement or the architect’s request, the contractor pays to uncover and replace it, even if the work is fine. If not, it depends on whether the work conforms. If it conforms, the owner pays through a price and time adjustment. If it doesn’t, the contractor pays to fix it.Who pays to uncoverthe work?Covered against arequirement or request?YESContractor payseven if the work is fineNO → DOES IT CONFORM?YesOwner paysprice + timeNoContractorpays to fixWhy it was covereddecides who pays.
Question

An RFI answer changes the price and the permitted design. Does calling it a clarification get around the change process?

Hazardous conditions during construction

If the contractor hits an unaddressed hazardous material posing serious risk (like suspected asbestos), it stops affected work and notifies the owner and architect. The owner investigates and makes it safe.

Requests for information

A request for information (RFI), often on AIA G716, asks about an unexpected condition, omission, or conflict. Good RFIs cite location, documents, and the exact question (unlike the immortal "please clarify the wall," which you'll still receive).

  • If the answer shifts scope, cost, time, or the permitted design, route it through the change process and any agency approval. When an RFI bundles a price request, give the technical answer in writing and handle cost separately.
  • When drawings and specs conflict, interpret them impartially in writing.
  • Under B101, answering RFIs already answered in the documents is an additional service.

K56 / Quick check

Quiz

10 questions
← Quiz list
Question 1 of 10Choose one answer
Under A201, which of the following describes the role of the shop drawings the contractor submits?

TLDR  ·  Quick Reference

Submittal route
Sub or vendor → general contractor reviews, coordinates, and approves → architect reviews for design conformance. Skip the contractor and it goes back unreviewed.
Submittals
Shop drawings, product data, and samples show how the contractor plans to comply, never becoming Contract Documents.
Who checks what
The contractor's stamp certifies review, approval, measurements, and coordination. The architect checks design conformance only.
Deviations
Must be called out and approved through the change process. An unflagged change isn't approved just because your stamp hit the sheet.
Delegated design
Owner and architect set performance criteria, the contractor's engineer seals the design, and the architect checks design conformance and fit.
Stopping work
The owner (unfixed nonconforming work), an unpaid contractor, and the building official can stop work. The architect can't.
Covered work
Covered against a requirement or request means contractor pays with no extra time even if fine. Properly covered work earns price and time if conforming, or contractor pays if not.
Request for information (RFI)
A question that never approves extra cost, time, or a contract change on its own.

Student Q&A

Questions students asked about K56, with answers from The Exit Club. All questions

Loading questions…

Sources & handbook wording

K56 · Knowledge of procedures for reviewing shop drawings, submittals, and samples.

  1. AIA A201–2017 ↗

    Architect observation/authority limits. Shop drawings, product data, samples and RFIs

  2. CSE Candidate Handbook ↗

    Published content outline, Project Bidding and Construction, K56. April 2026 handbook PDF p.16 · Official knowledge-statement scope only. Technical notes also draw on the itemized references.

  3. Supplemental primary source: AIA G710–2017 ↗

    Architect’s Supplemental Instructions. Minor changes without a Contract Sum or Contract Time adjustment

  4. Supplemental primary source: AIA G714–2017 ↗

    Construction Change Directive. Directed changes before full agreement on adjustments

  5. Supplemental primary source: AIA G716–2004 ↗

    Request for Information. Clarification without authorizing a change