K10 — Project team responsibilities
K10 is the project org chart with teeth, and one of the chapters the exam hits hardest. Almost every question boils down to whose lane this is and which contract drew the lines. During design, the American Institute of Architects (AIA) owner–architect agreement (B101) sets the rules. During construction, A201 (General Conditions) governs: with no contract between architect and contractor, every construction-phase power flows straight from A201.
Roles through the phases
| Phase | Owner | Architect | Contractor |
|---|---|---|---|
| Predesign | Goals, budget, program, site info | Programming or site studies, if hired | Not involved yet |
| Design phases | Reviews and approves each phase | Design, consultants, code and cost checks, plan check | Early pricing in construction manager (CM) at risk or design-build |
| Bidding | Picks contractor, signs contract | Answers bidders, issues addenda | Bids or negotiates |
| Construction | Pays, decides promptly, can stop work | Site visits, payment certificates, changes, claims | Builds, controls methods and safety |
| Closeout | Accepts work, records Notice of Completion | Completion inspections | Punch list, warranties, lien releases |
Who holds which power
Keep this lookup handy for every "what should the architect do next?" prompt.
| Power | Who has it under A201 |
|---|---|
| Stop the work | The owner (for cause), the building official, and an unpaid contractor. Never the architect. |
| Reject nonconforming work, require testing | The architect |
| Accept nonconforming work for a lower price | The owner |
| Means, methods, sequences, safety | The contractor alone |
| Direct subs and workers | The contractor |
| Minor change, no cost or time shift | The architect alone (G710) |
| Change order | Owner, contractor, and architect (G701) |
| Construction change directive | Owner and architect (G714), before cost or time is agreed |
| Certify payment | The architect, within 7 days |
| First decision on a claim | Initial Decision Maker (IDM): the architect unless someone else is named |
| Interpret the documents | The architect, fairly and in writing |
| Building permit | The contractor, unless documents say otherwise |
| Certificate of Occupancy | The building official |
| Notice of Completion | The owner records it |
If one line survives exam day, make it this one: the architect rejects, the owner stops. See K13, K47, K50, and K51.
Owner responsibilities
- Authorized representative: Names one person who can bind the owner. When two owner staffers or board members conflict, never pick a winner: route it to that representative.
- Program and decisions: Supplies a written program, realistic budget, and timely decisions.
- Site info: Furnishes surveys, legal limitations, utility locations, and a legal description, and pays for the geotechnical investigation.
- Proof of financing (before start): The contractor may request reasonable evidence that the owner can pay.
- Proof of financing (after start): Triggered only by a missed payment, a written reasonable concern, or a material contract-sum shift. With no proof, the contractor can stop.
- Fees and code duty: Pays for approvals, easements, assessments, and charges outside contractor-assigned permits. Owner approval of drawings never shifts your duty to design to code.
Owner's right to stop the work
If the contractor ignores nonconforming work, the owner can issue a written order to stop the work. The architect rejects work, never stops it.
Conversely, if the architect fails to certify payment within 7 days, or the owner fails to pay within 7 days of the due date, the contractor can stop after another 7 days' notice.
Owner's right to carry out the work
If the contractor fails to start fixing neglected work within 10 days of written notice, the owner can do it. The architect approves both the action and the amount first, then deducts the cost from the contractor's Certificate for Payment. A disagreeing contractor can file a claim.
Contractor responsibilities
- Site and document check: Signing confirms the contractor visited the site and knows the documents, flagging discrepancies through a request for information (RFI).
- Complementary documents: Contract documents are complementary and unranked under A201. When drawings and specs clash, the contractor asks for written direction instead of building the cheaper option.
- Code issues: No duty to audit drawings for code, yet the contractor must report any violation it spots. Knowingly building illegal work means paying to fix it.
- Means, methods, and safety: The contractor alone controls means, methods, techniques, sequences, procedures, and jobsite safety. If a specified method looks unsafe, it alerts owner and architect and proposes another.
- Permits and tests: Gets and pays for the building permit and contract-required tests unless stated otherwise. The owner hires building-code special inspectors (K53).
Unexpected conditions
- Concealed or unknown conditions: Notify owner and architect before disturbing the area and within 14 days of first seeing it.
- Investigation and adjustment: The architect investigates promptly and recommends an equitable adjustment if cost or time changes (a change order if everyone agrees, or a claim if anyone doesn't).
- Remains, archaeology, or unshown wetlands: Stop affected work immediately and notify. The owner secures restart approval while other areas keep going.
- Unaddressed hazardous material (like asbestos): Stop work in that area and notify, leaving testing and abatement to the owner.
Submittals
K56 covers submittal mechanics. Keep three contractor rules cold:
- Submittals show how the contractor plans to comply, and they are never contract documents.
- The contractor reviews and approves every submittal first. Shop drawings sent straight from a fabricator go right back to the contractor.
- Approval never excuses a deviation unless flagged in writing and specifically approved. Smuggling a cheaper faucet inside a 40-page shop drawing packet buys nobody an approval.
Architect responsibilities
You serve as an owner's representative from construction contract award until the final Certificate for Payment. Under B101, construction services extending more than 60 days past substantial completion are additional services, while a building-operations review within one year after substantial completion comes at no extra fee upon request.
- Site visits and reports: Visit at intervals matching construction progress (never exhaustive inspections), reporting progress, quality, and known defects or deviations to the owner.
- Field limits: You require compliance through the contract without controlling safety or directing crews. Spot an obvious hazard like an unshored trench? Warn people in danger immediately, then tell contractor and owner.
- Submittal review: Review solely for the design concept. Dimensions, quantities, and installation stay with the contractor.
- Certifying payment: Certify what's due within 7 days, explaining anything withheld. Claiming 80% complete with 60% built earns a certificate for 60%.
- Rejecting work: Reject nonconforming work and notify the owner, who alone may accept it (usually for a credit). Neither paying nor moving in counts as acceptance.
- Changes and closeout: Prepare change orders and directives, order minor changes, and inspect for substantial and final completion.
- Interpretations and claims: Interpret fairly and in good faith despite the owner's checks. As IDM, act within 10 days (after 30 days with no decision, the claimant may move to mediation).
Worked example: what should the architect do next?
The inspector fails the underground plumbing, and the contractor plans to pour the slab tomorrow morning. Resist the urge to stand in front of the concrete truck yelling "stop!" Instead, warn the contractor in writing that covering failed work will be rejected and alert the owner immediately (since the owner or inspector can stop it). Classic traps have you stopping work, directing a sub, or shrugging it off as sequencing.
Communication routes
- Owner and contractor: May talk directly, with the architect looped into anything affecting its services.
- Architect's consultants: Route through the architect.
- Subcontractors and suppliers: Route through the contractor.
- Owner's separate contractors: Route through the owner.
Question
On a site visit, the architect sees a wall framed in the wrong place. Can the architect order the contractor to stop the work?
Construction-administration scope
Essential services buildings, public schools and community colleges, and hospitals carry state-mandated observation and reporting, requiring heavier construction administration (CA) scope (K24). Adding a construction manager never strips the architect's contract administration decisions (certifying payment, signing change orders) and never shrinks your liability (K55).
Common administration documents
Most construction paperwork uses the AIA G forms (K5), while two closeout documents never come from the architect:
- Certificate of Occupancy: Issued by the building official to the owner after the final inspection passes.
- Notice of Completion: Signed and recorded by the owner at the county recorder within 15 days after completion to shorten lien deadlines (K46).
K10 / Quick check
Quiz
TLDR · Quick Reference
- Owner
- Names one authorized representative, furnishes program, budget, surveys, and site info, pays for approvals and easements, decides promptly, and pays.
- Contractor
- Builds to the documents, controls means, methods, sequences, and safety, and obtains the building permit unless stated otherwise.
- Architect
- Owner's representative from contract award to final payment: site visits, payment certificates within 7 days, rejecting work, fair interpretations, and initial claim decisions.
- Stop vs. reject
- Owner (for cause), building official, and an unpaid contractor can stop work. The architect can only reject it.
- Who signs changes
- Minor change (G710), architect alone. Change order (G701), all three. Construction change directive (G714), owner and architect before cost or time is agreed.
- Owner fixes it
- After 10 days of written notice with no start, the owner can fix neglected work once the architect approves action and cost, deducted from payment.
- Hidden conditions
- Notice before disturbing and within 14 days, then architect investigates. For remains, archaeology, wetlands, or hazardous material, stop affected work and notify.
- Submittals
- Not contract documents. Contractor reviews and approves first, and the architect reviews solely for the design concept.
Student Q&A
Questions students asked about K10, with answers from The Exit Club. All questions
Loading questions…
Something in K10 unclear? Log in to ask a question.
Log in to askYour questions
Sources & handbook wording
K10 · Knowledge of architect and project team roles and responsibilities in all phases of projects.
- AIA B101–2017 ↗
B101–2017 §§3.1–3.6, including §3.6.1.3 construction phase start and end, §3.6.2.5 Initial Decision Maker and §3.6.6.5 operations meeting. §4.2.4. Article 5
- AIA A201–2017 ↗
A201–2017 §§1.1–1.2. Article 2. §§3.1–3.3, 3.7, 3.9, 3.12. §4.2. Article 7. §§9.2–9.10. §10.3. §§12.3, 13.4. §15.2. Relevant supplied text verified.