K47 — Changes during construction
Knowledge of methods and procedures for implementing changes during construction.
Every construction change under A201 boils down to two questions: does it shift price or schedule, and does everyone agree on the adjustment? Answer those two, and the right form hands itself to you.
Change-order process
- An owner request, field condition, or contractor's written notice starts it.
- The architect sends a proposal request (G709) describing the work.
- The contractor returns cost and schedule impact.
- The architect reviews it with the owner.
- Owner passes? Notify the contractor, and stop there.
- Owner approves? The architect prepares the change order (G701), and all three sign.
In the full lesson
- Change-order process
- Supplemental instructions: G710
- Change order: G701
- Construction change directive: G714
- Claims and disputes
- Which tool fits?
- TLDR quick reference
- Quiz, 10 questions
- Flashcards
- Audio lesson
Keep going with a Study Pass.
ADMIT ONECALIFORNIA CSE
Study Pass
90DAYS OF
FULL ACCESS
FULL ACCESS
PERSONAL STUDY PASS
Regular price $349 USD Launch sale price $179
Launch sale —
limited time only
One payment.
No automatic renewal.
Already a member?Log in