K28 — CALGreen

CALGreen, the California Green Building Standards Code (Title 24, Part 11), spans five areas: (1) planning and design, (2) energy efficiency, (3) water efficiency and conservation, (4) material conservation and resource efficiency, and (5) environmental quality. Every covered project meets the mandatory measures, while the voluntary tiers raise the bar further.

Because CALGreen is one of the most heavily tested topics on the California Supplemental Examination (CSE), take it in two clean passes: learn which projects trigger it first, then lock in the numbers division by division. Most questions target nonresidential buildings (Chapter 5), with a quick housing comparison (Chapter 4) waiting near the end.

CALGreen’s five areas, with the numbers to knowFive rows. 1, planning and design: stormwater under 1 acre uses BMPs or local rules, 1 acre or more uses the state permit. Bike parking for 20 percent of peak daily visitors and 10 percent of tenant-occupants. EV capable spaces plus chargers. Outdoor light limited by BUG ratings for each lighting zone. 2, energy efficiency: points to Part 6, the Energy Code. 3, water: toilets 1.28 gallons per flush, wall urinals 0.125, showerheads 1.8 gallons per minute, lavatory faucets 0.5, submeters for tenants over 100 gallons a day in buildings over 50,000 square feet, landscaping by MWELO. 4, materials and resources: divert 65 percent of construction waste, entries get 2 feet of hard finish plus a 4-foot cover, commission new buildings of 10,000 square feet or more. 5, environmental quality: MERV 13 filters, during construction too, low-emitting finishes, no smoking within 25 feet of entries, STC 50 walls near an airport or freeway. Each area is a division of Chapter 5, numbered 5.1 to 5.5.CALGreen’s five areas, with the numbers to know1Planning and designStormwater: BMPs under 1 acre,the state permit at 1 acre or moreBikes: 20% of peak daily visitors10% of tenant-occupantsEV capable spaces plus chargersOutdoor light: BUG limits by lighting zone2Energy efficiencyPoints to Part 6, the Energy Code3WaterToilets 1.28 gpfWall urinals 0.125 gpfShowerheads 1.8 gpmLavatory faucets 0.5 gpmSubmeters: tenants over 100 gal/dayin buildings over 50,000 SFLandscapes follow MWELO4Materials and resourcesDivert 65% of construction wasteEntries: 2 ft hard finish plus a 4 ft coverCommission new buildings of 10,000 SF+5Environmental qualityMERV 13 filters, during construction tooLow-emitting finishesNo smoking within 25 ft of entriesSTC 50 walls near an airport or freewayEach area is a division of Chapter 5, numbered 5.1 to 5.5.CALGreen’s five areas, with the numbers to knowFive rows. 1, planning and design: stormwater under 1 acre uses BMPs or local rules, 1 acre or more uses the state permit. Bike parking for 20 percent of peak daily visitors and 10 percent of tenant-occupants. EV capable spaces plus chargers. Outdoor light limited by BUG ratings for each lighting zone. 2, energy efficiency: points to Part 6, the Energy Code. 3, water: toilets 1.28 gallons per flush, wall urinals 0.125, showerheads 1.8 gallons per minute, lavatory faucets 0.5, submeters for tenants over 100 gallons a day in buildings over 50,000 square feet, landscaping by MWELO. 4, materials and resources: divert 65 percent of construction waste, entries get 2 feet of hard finish plus a 4-foot cover, commission new buildings of 10,000 square feet or more. 5, environmental quality: MERV 13 filters, during construction too, low-emitting finishes, no smoking within 25 feet of entries, STC 50 walls near an airport or freeway. Each area is a division of Chapter 5, numbered 5.1 to 5.5.CALGreen’s five areas,with the numbers to know1Planning and designStormwater: BMPs under 1 acre,the state permit at 1 acre or moreBikes: 20% of peak daily visitors10% of tenant-occupantsEV capable spaces plus chargersOutdoor light: BUG limits by lighting zone2Energy efficiencyPoints to Part 6, the Energy Code3WaterToilets 1.28 gpfWall urinals 0.125 gpfShowerheads 1.8 gpmLavatory faucets 0.5 gpmSubmeters: tenants over 100 gal/dayin buildings over 50,000 SFLandscapes follow MWELO4Materials and resourcesDivert 65% of construction wasteEntries: 2 ft hard finish plus a 4 ft coverCommission new buildings of 10,000 SF+5Environmental qualityMERV 13 filters, during construction tooLow-emitting finishesNo smoking within 25 ft of entriesSTC 50 walls near an airport or freewayEach area is a division ofChapter 5, numbered 5.1 to 5.5.

CALGreen scope and organization

Who writes it

California wrote CALGreen from scratch rather than adapting a national model code, and four state agencies split adoption by building type:

Agency Buildings
Building Standards Commission (BSC) Nonresidential buildings, including offices, stores, and warehouses
Department of Housing and Community Development (HCD) Housing, including homes, apartments, hotels, and dorms
Division of the State Architect (DSA) Public K–12 schools and community colleges
Office of Statewide Health Planning and Development (OSHPD), now the Department of Health Care Access and Information (HCAI) Hospitals, skilled nursing facilities, and correctional treatment centers (subject only to the outdoor water use rule)
  • The Energy Commission writes the Energy Code, not CALGreen. Local building departments enforce CALGreen through plan review and inspection, while DSA enforces it for public schools.
  • To make CALGreen stricter, a city or county adopts express findings tied to local climatic, geological, or topographical conditions and files the amendment with the BSC. It takes effect the moment it is filed.
  • The permit application date sets the code edition, never the start of design or construction. Applications submitted on or after January 1, 2026 fall under the 2025 edition.

When it applies

Project Does CALGreen apply?
Any new building Yes
Nonresidential addition 1,000 square feet or more
Nonresidential alteration Permit valuation of $200,000 or more
Construction waste diversion in any addition or alteration Whenever a permit is required, even below those triggers

Only the added or altered area has to comply. Mixed-occupancy buildings follow each occupancy's own chapter (HCD for the apartments upstairs, BSC for the retail below). For shell buildings, CALGreen covers the initial tenant improvements, while later tenant build-outs are judged on their own against the 1,000 square foot and $200,000 triggers.

How the code is organized

Chapter What's in it
4 Residential mandatory measures
5 Nonresidential mandatory measures, in Divisions 5.1 to 5.5 (one per area)
Appendix A4 / A5 Residential / nonresidential voluntary tiers

You and your consultants complete the CALGreen mandatory measures checklist and bind it into the permit set, keying every item to the exact drawing sheet or spec section where it is met.

Question

The parking plan marks five stalls for clean air vehicles. Does that take care of CALGreen’s EV charging requirement?

(1) Planning and design

Division 5.1 stays outdoors: mud and runoff during construction, drainage around the building, bikes and electric vehicles, and night-sky lighting.

Rain and soil during construction

  • Under 1 acre (outside a larger common plan of development or sale): follow the local stormwater or erosion control ordinance, or use best management practices (BMPs) like dry-weather grading, mulching, silt fences, inlet protection, and tidy stockpiles.
  • 1 acre or more (or under 1 acre inside a larger common plan): obtain the state Construction General Permit under the National Pollutant Discharge Elimination System (NPDES), with a Storm Water Pollution Prevention Plan (SWPPP) (K27). Post-construction runoff must match pre-project levels, mainly through low impact development (LID) that lets rain soak in where it lands.

Water around the finished building

Grading and drainage plans must show how surface water stays out of the building using swales, French drains, or retention gardens. Additions and alterations that leave the drainage path untouched are exempt.

Getting there without a gas car

Count bike parking from people, never from car stalls:

  • Short-term (visitors): permanently anchored racks within 200 feet of the visitors' entrance, visible to passers-by, sized for 20 percent of peak daily visitors. Required on any new project, addition, or alteration expected to draw visitors.
  • Long-term (employees): secure parking for 10 percent of tenant-occupants (at least one) inside a covered lockable enclosure, lockable bike room, or bike lockers. Additions and alterations cover 10 percent of the tenant-occupants they add.

For example, a new office expecting 40 visitors on its busiest day with 120 tenant-occupants needs racks for 8 visitor bikes and secure stalls for 12 employee bikes.

Electric vehicle charging

Keep two electric vehicle (EV) definitions straight:

  • An EV capable space has the infrastructure without the charger: a raceway from the panel to the stall plus panel space and capacity for a future charger circuit, with both the panel and raceway end labeled "EV CAPABLE".
  • An EV charging station (EVCS) is an EV capable space with the actual charger installed. Chargers may be Level 2 or direct current fast chargers (DCFC), provided at least one is Level 2.

New nonresidential buildings size their EV spaces from total on-site parking, rounding up. Notice two exam favorites: EVCS count inside the EV capable total (never stacked on top), and offices and stores require more installed chargers than other building types. Learn these rows:

Total parking spaces EV capable (including the EVCS) EVCS, other buildings EVCS, offices and stores
0–9 0 0 0
10–25 4 2 3
26–50 8 4 6
201 or more 20% of all spaces 50% of the EV capable 75% of the EV capable

Between 51 and 200 spaces, the code's table keeps stepping the counts up. Quick math check: a 40-space store needs 8 EV capable spaces with 6 chargers inside that 8. A 240-space warehouse needs 48 EV capable spaces (20 percent), with 24 chargers (50 percent of 48).

  • Truck charging: warehouses, stores, offices, and factories with planned loading docks must reserve electrical capacity for future medium- and heavy-duty truck charging.

Designated parking for "clean air vehicles" (zero-emitting, high-efficiency, carpool, and vanpool) is not mandatory. It lives strictly in the voluntary tiers, and a painted stall never substitutes for EV charging. Housing follows its own EV rules in the residential section.

Lights at night

Light pollution reduction borrows the Energy Code's lighting zones, from LZ0 (very dark) to LZ4 (brightest urban), and caps each outdoor fixture's BUG rating (Backlight, Uplight, and Glare). Limits tighten near property lines, and area lighting allows zero uplight (U0) in every zone because the night sky has never asked for floodlighting. Emergency lighting is exempt.

(2) Energy efficiency

CALGreen's energy division sets no energy rules of its own: it simply points down the hall to the California Energy Code (Part 6), written by the Energy Commission (K37). Neither paperwork package covers for the other, which means every permit set needs both an Energy Code report and a CALGreen checklist.

Question

A wall-mounted urinal flushes 0.5 gallons. Does it meet CALGreen?

(3) Water efficiency and conservation

Drought shapes every pipe in Division 5.3, indoors and out.

Question

A practice question says CALGreen requires a 20 percent wastewater reduction. Is that a mandatory measure?

Indoor fixtures

Fixture Maximum
Toilets (water closets) 1.28 gallons per flush
Wall-mounted urinals 0.125 gallons per flush
Showerheads 1.8 gallons per minute (multiple heads on one valve cannot exceed 1.8 combined)
Lavatory faucets (nonresidential) 0.5 gallons per minute
  • Watch the units: flush and minute swap easily on exam choices.
  • Homes vs. offices: residential unit lavatories allow 1.2 gallons per minute, which won't fly in an office restroom.
  • Labels and inspections: tank-type toilets and showerheads carry the Environmental Protection Agency's (EPA's) WaterSense label, checked both on construction documents and at inspection.
  • Alterations: new fixtures in additions or alterations follow the same limits above.

Mandatory CALGreen has no percentage water-reduction target. Hitting every fixture limit is full compliance. Percentage cuts exist only in the voluntary tiers.

Meters

  • Over 50,000 square feet: any new building or addition needs a submeter for each tenant expected to use more than 100 gallons a day (restaurants, laundries, salons, medical offices).
  • Any building size: any new building or addition must submeter any tenant expected to use more than 1,000 gallons a day.

Outdoor water

Indoor fixture savings never excuse the landscape. New irrigated landscapes (and large rehabilitated ones) follow the state Model Water Efficient Landscape Ordinance (MWELO) or a stricter local rule, requiring a water budget, climate-adapted plants, and weather- or soil-moisture-based irrigation controllers.

(4) Material conservation and resource efficiency

Division 5.4 covers weather durability, jobsite waste, recycling, commissioning, and embodied carbon.

Keeping water out of the building

  • Exterior walls and foundations follow California Building Code (CBC) weather protection or manufacturer instructions, whichever is stricter, and flashing must tie into a drainage plane.
  • Landscape sprinklers cannot spray the building.
  • Primary exterior entries need nonabsorbent floor and wall finishes for at least 2 feet around the door, plus an awning, roof overhang, or door recess at least 4 feet deep (or an equivalent barrier).

Construction waste

Divert at least 65 percent of nonhazardous construction and demolition waste (or meet a stricter local rule), a mandate that applies to every permitted addition or alteration regardless of size or cost. Prove compliance, usually one of two ways:

  1. A construction waste management plan listing materials, on-site sorting vs. mixed hauling, receiving facilities, and measurements tracked consistently by weight or volume (never mixing both).
  2. A waste hauler that documents the diversion rate.

Keep site clearing separate: excavated soil, trees, stumps, and rocks never pad the 65 percent calculation because they carry their own 100 percent reuse or recycling rule. On additions and alterations, list universal waste (fluorescent lamps, ballasts, mercury thermostats) on the construction documents for proper disposal.

Recycling after move-in

Provide readily accessible recycling areas for at least paper, cardboard, glass, plastics, organic waste, and metals.

Commissioning

Commissioning verifies that building systems actually deliver what the owner needs, and it is mandatory on new buildings of 10,000 square feet or more. Unconditioned warehouses, open parking garages, and tenant improvements under 10,000 square feet are exempt.

Commissioning runs the whole projectA timeline across predesign, design, construction and occupancy. The owner’s project requirements (OPR) come first, in predesign. The basis of design (BOD) follows in design. The commissioning plan is finished before the permit is issued. Installation checks and functional tests happen in construction, and training and records at occupancy. Functional testing checks each system against the OPR, which startup alone doesn’t do.Commissioning runs the whole projectIt starts before design, not at the end.PredesignDesignConstructionOccupancyOPRWhat the owner needsBODHow the design does itChecks + functional testsDoes it really work?Training + recordsCan the staff run it?Commissioning plan: before the permitFunctional testing checks each system against the OPR. Startup alone doesn’t.Commissioning runs the whole projectA timeline across predesign, design, construction and occupancy. The owner’s project requirements (OPR) come first, in predesign. The basis of design (BOD) follows in design. The commissioning plan is finished before the permit is issued. Installation checks and functional tests happen in construction, and training and records at occupancy. Functional testing checks each system against the OPR, which startup alone doesn’t do.Commissioning runsthe whole projectPredesignDesignConstructionOccupancyOPRWhat the owner needsBODHow the design does itChecks + functional testsDoes it really work?Training + recordsCan the staff run it?Commissioning plan: before the permitFunctional testing checks each systemagainst the OPR. Startup alone doesn’t.
Step What it is
Owner's project requirements (OPR) Owner goals (energy, water, indoor air quality, operating hours), written before design starts
Basis of design (BOD) How the design team's systems satisfy the OPR, written during design
Commissioning measures Incorporated directly into the construction documents
Commissioning plan Systems to test, team roles, schedule, and test procedures, complete before the permit is issued
Functional performance testing Proves components, systems, and system interconnections operate as specified
Systems manual and training Reference guide and hands-on training for building operators
Commissioning report Final closeout report delivered to the owner

Memorize the timing rhyme: OPR before design, BOD during design, commissioning plan before permit.

  • Equipment startup only proves the machine turns on and runs. Functional performance testing proves it actually follows the OPR. For heating, ventilation, and air conditioning (HVAC), lighting, and water heating, Energy Code commissioning runs with CALGreen as one process.
  • Commissioning sits outside American Institute of Architects (AIA) B101 basic services: if the owner wants you to provide it, add a separate scope and fee (K57).

Testing and adjusting

New buildings under 10,000 square feet, plus new systems in additions and alterations, get testing and adjusting instead: a written test plan, HVAC balancing before occupancy per a recognized balancing organization's procedures, a signed final report, and an operation and maintenance manual for the owner.

Embodied carbon (the carbon released making materials and putting up the building) applies to nonresidential buildings of 50,000 square feet or more, new or altered (additions count the existing building's area too). Three compliance paths work: cut embodied carbon in a whole-building life cycle assessment, specify products below set carbon limits, or (for an existing building) reuse a set share of the structure and enclosure.

(5) Environmental quality

Division 5.5 guards what occupants breathe and hear.

During construction

  • Seal duct openings with tape, plastic, or sheet metal from rough-in until startup.
  • If permanent HVAC runs during construction, fit return grilles with at least Minimum Efficiency Reporting Value (MERV) 13 filters and replace every filter right before occupancy.

Finish materials

Finish submittals must prove emissions compliance directly. A safety data sheet never counts as emissions evidence, no matter how many times contractors try sliding one into the submittal log.

Material Standard
Adhesives, sealants, and caulks Volatile organic compound (VOC) limits from the local air district or South Coast Air Quality Management District (SCAQMD Rule 1168)
Paints and coatings VOC limits from the California Air Resources Board (CARB)
Carpet, resilient flooring, insulation, acoustical ceilings, and wall panels California Department of Public Health (CDPH) emissions test ("Specification 01350")
Composite wood (plywood, particleboard, medium-density fiberboard, or MDF) CARB formaldehyde limits

At least 80 percent of resilient flooring area must pass the CDPH test.

In the finished building

  • Filters: mechanically ventilated buildings require MERV 13 or better on both outside and return air, installed fresh right before occupancy (replacing any MERV 13 filters used during construction).
  • Smoking: where an outdoor smoking area is provided, no smoking within 25 feet of entries, outdoor air intakes, and operable windows.
  • Fireplaces: sealed units only (such as direct-vent gas), plus woodstoves or pellet stoves meeting EPA emission limits.
  • Moisture and fresh air: moisture control follows the CBC, outside air follows Energy Code ventilation rules, and spaces with demand-controlled ventilation need carbon dioxide (CO2) sensors.
  • Noise: inside a 65 dB community noise equivalent level (CNEL) contour (airport, freeway, railroad, or industrial site), exterior walls and roofs need composite Sound Transmission Class (STC) 50 and windows need STC 40.
  • Refrigerants: zero chlorofluorocarbons (CFCs) or halons in HVAC, refrigeration, or fire suppression systems.
Question

A new office has a 20-space parking lot. The plans show 4 EV capable spaces and no chargers. Does plan check need to see chargers installed?

Residential buildings (Chapter 4)

Chapter 4 mirrors Chapter 5's five divisions, keeping the same toilet, urinal, and showerhead limits, 65 percent waste rule, low-emitting finishes, and sealed fireplaces. Focus on the five places where housing diverges:

Topic Housing (Chapter 4) Nonresidential (Chapter 5)
Additions and alterations Covered only when adding conditioned area, volume, or size 1,000 square feet or $200,000
EV, house or townhouse with an attached garage One EV capable space per unit The EV table above
EV, apartments and hotels Apartments: one EV ready space (low-power Level 2 outlet) per unit. Hotels: a share of spaces EV ready and a share with Level 2 chargers. The EV table above
Lavatory faucets 1.2 gallons per minute in dwelling units, 0.5 in common areas 0.5 gallons per minute
Bathroom exhaust ENERGY STAR fan ducted outside in every bathroom, with a humidity control (unless part of a whole-house system) Not in CALGreen (California Mechanical Code covers it, K16)

Voluntary measures and reference standards

  • Tier 1 and Tier 2: for nonresidential buildings, Appendix A5 stacks extra savings on top of every mandatory measure. Tier 1 adds things like an indoor water cut and stalls reserved for clean air vehicles, and Tier 2 asks for more of each.
  • Voluntary tiers become code only when a city or county adopts them by local amendment, at which point the local building department enforces them. Putting a tier in the owner–architect contract makes it a contract promise, never code.
  • LEED (Leadership in Energy and Environmental Design) is a private, voluntary rating system. LEED certification never replaces code compliance, and CALGreen commissioning is narrower in scope than LEED's.

K28 / Quick check

Quiz

25 questions
← Quiz list
Question 1 of 25Choose one answer
An owner plans a 1,200-square-foot addition to an existing one-story office building. The architect is preparing the CALGreen mandatory measures checklist for the permit application. Which of the following should the checklist cover?

TLDR  ·  Quick Reference

CALGreen
California Green Building Standards Code (Title 24, Part 11). Mandatory measures apply everywhere, while voluntary tiers bind only when a city or county adopts them. The California Energy Commission writes Part 6, not CALGreen.
Who and when
Building Standards Commission (BSC) for nonresidential, Department of Housing and Community Development (HCD) for housing, Division of the State Architect (DSA) for schools. Applies to new buildings, additions of 1,000 SF or more, and alterations of $200,000 or more.
Site
Under 1 acre uses local rules or best management practices (BMPs), while 1 acre or more triggers the state permit. Bikes: 20% of peak daily visitors within 200 ft, 10% of tenant-occupants.
Electric vehicles (EVs)
EV capable spaces with EV charging stations (EVCS) counted inside. 10–25 spaces: 4 and 2 (3 at offices/stores). 26–50: 8 and 4 (6). Over 200: 20%, with 50% charged (75% at offices/stores). At least one Level 2.
Water
Toilets 1.28 gpf, wall urinals 0.125, showerheads 1.8 gpm, office lavatories 0.5 (homes 1.2). No mandatory % cut. Submeters over 50,000 SF at 100 gal/day (1,000 gal/day at any size).
Materials
Divert 65% of construction waste on any permitted addition or alteration, and 100% of land-clearing debris. Entries get 2 ft of nonabsorbent finish plus a 4 ft cover.
Commissioning
New buildings of 10,000 SF or more. Owner's project requirements (OPR) before design, basis of design (BOD) during design, commissioning plan before permit. Smaller buildings get testing and adjusting.
Air
Minimum Efficiency Reporting Value (MERV) 13 return filters if permanent heating and cooling runs during construction, replaced with fresh MERV 13 filters before occupancy. 80% of resilient flooring tested, no smoking within 25 ft.

Student Q&A

Questions students asked about K28, with answers from The Exit Club. All questions

Loading questions…

Sources & handbook wording

K28 · Knowledge of methods and procedures for complying with California Green Building Standards Code (CALGreen) related to design and construction.

  1. CAB CSE Handbook, April 2026 ↗

    PDF p.13, K28. Official scope only

  2. 2025 CALGreen: Nonresidential Mandatory Measures ↗

    Divisions 5.1–5.5, including embodied carbon in Sections 5.105 and 5.409. CAB-listed chapter

  3. 2025 CALGreen: Appendix A5 ↗

    Divisions A5.1–A5.6. Voluntary measures and Tier 1 and Tier 2. CAB-listed appendix

  4. 2025 CALGreen: Residential Mandatory Measures ↗

    Chapter 4. CAB-listed chapter

  5. 2025 CALGreen: Administration ↗

    Chapter 1. Adopting agencies, local amendments, effective date

  6. 2025 CALGreen: Green Building (scope) ↗

    Sections 301–303. New buildings, 1,000 SF additions, $200,000 alterations, mixed occupancy

  7. California Building Standards Commission: 2025 Title 24 California Code Changes ↗

    Summary of the 2025 changes, in effect January 1, 2026, including CALGreen bicycle parking and EV charging · Supplemental primary-source clarification. Not a claim that this particular page is on CAB’s exam reference list.

  8. 2025 California Energy Code: Subchapter 3, Nonresidential Mandatory Requirements ↗

    Section 120.8. Energy Code commissioning that runs with CALGreen's

  9. AIA B101–2017 ↗

    Basic services and separately assigned commissioning services