K2 — Project scope & schedule
Agencies control two things: what gets built and when. The exam divides the road to occupancy into three gates (planning, plan check, and inspection) and tests their order and realistic durations.
Question
A theater conversion needs a use permit that could change its hours and access. Will a fully detailed construction set guarantee the approval?
01 / Entitlement approval
An entitlement is planning permission for a use or development, like a conditional use permit (K19). Handle it during schematic design (SD) and design development (DD): never sink money into construction documents before Planning says yes, since it can still reshape the size, layout, parking count, or hours of operation.
- 3–12 months for small or medium projects, and 6–24 months for large or complex ones.
- Environmental review, vocal neighbors, continued hearings, and appeals push you straight toward the long end.
02 / Plan check and agency review
Once entitled, the team draws construction documents (CD), packing the Energy Code forms (K37) and CALGreen checklist (K28) right inside. Building, Planning, Fire, and Public Works check the set against both the codes and your conditions of approval.
- 1–3 months for small or medium projects, and 2–6 months for large or complex ones.
Plan check is a loop, not a line: collect comments, fix every sheet they touch, file a resubmittal, and usually go around again. One fire-access comment moving a driveway ripples across site, civil, and landscape sheets. Catch every ripple before resubmitting, or plan check happily invites you back for another round.
Question
The required inspection hasn’t happened yet. Does the permit holder have to give safe access and leave the work visible until it does?
03 / Building permit and construction
The building permit comes before the work it covers, followed by the building department's own inspections.
- 6–12 months for small or medium projects, and 6–24 months for large or complex ones.
- The building official must approve work to date before the contractor goes any further.
- The permit holder provides safe access and leaves work exposed until approved: rebar and under-slab pipes before concrete, rough plumbing and electrical before drywall.
- An architect's site visit never substitutes for a building inspection.
Final inspection and occupancy
After final inspection, the building official issues the Certificate of Occupancy to the owner. The architect's certificate of substantial completion is a contract document and never replaces it (K41): one settles the contract between the parties, while the other lets real people walk inside. Alterations keeping the existing legal occupancy may close out with just a final permit sign-off.
How agencies change the scope
| Agency | How it can change the project |
|---|---|
| Planning | Conditions of approval on height, setbacks, parking, landscaping, materials, or hours |
| Environmental review | Mitigation like sound walls, habitat buffers, or traffic improvements |
| Fire | Access roads, truck turnarounds, hydrants, sprinklers, and alarms |
| Public Works | Street and sidewalk improvements, right-of-way dedications, stormwater treatment |
| Utilities | Transformer and meter locations, service upgrades, easements |
| Health | Kitchen, pool, or medical layouts and finishes |
Conditions of approval aren't hearing-night suggestions: they stay in your drawings until Planning formally agrees to change them.
State and regional reviews
Spot these at kickoff, before they ambush your schedule at permit time (K6).
| Review | When it applies | Schedule effect |
|---|---|---|
| California Environmental Quality Act (CEQA) | Discretionary approvals of non-exempt projects | Often the longest stretch of entitlement |
| Coastal development permit | Development in the coastal zone | Before the building permit |
| Division of the State Architect (DSA) | Public K–12 schools and community colleges | Replaces the local building department. No construction until DSA approves in writing. |
| Department of Health Care Access and Information (HCAI) | Hospitals and some other health facilities | Handles both plan review and inspection |
| Water Boards | Construction disturbing 1 acre or more | Construction General Permit coverage and stormwater plan before grading |
| County health department | Restaurants, markets, pools | Plan approval before construction |
Discretionary approvals (CEQA, coastal permits, entitlements) always precede ministerial plan check and the building permit. Asked what comes first? Pick the discretionary gate (K42).
Question
The building department quotes four weeks for plan check. Should the schedule show the permit four weeks after submittal?
Time allowances in the architect’s schedule
- Under the American Institute of Architects (AIA) B101, your schedule budgets for owner decisions, consultant work, and agency review, not just drafting.
- A dependency is work stuck waiting on an earlier step: pick kitchen equipment late, and engineering plus everything downstream slides.
- A quoted review window covers one review, never the permit date. Four weeks of review, two of corrections, and three of recheck already total nine weeks, before fees or utility clearances. The review time isn't the permit date.
K2 / Quick check
Quiz
TLDR · Quick Reference
- Entitlement
- Runs during schematic design and design development, before construction documents. 3–12 months (small/medium) or 6–24 months (large/complex).
- Plan check
- A loop of comments, coordinated fixes, and resubmittals. 1–3 months (small/medium) or 2–6 months (large/complex).
- Construction
- 6–12 months (small/medium) or 6–24 months (large/complex). Work stops at each inspection until the building official approves it.
- Occupancy
- The building official issues the Certificate of Occupancy to the owner. Substantial completion never replaces it.
- Scope impacts
- Conditions of approval, environmental mitigation, fire access, Public Works improvements, health layouts, and utility easements can all reshape the design.
- Order
- Discretionary approvals like California Environmental Quality Act (CEQA) review and coastal permits precede ministerial plan check and the building permit.
- State reviews
- Division of the State Architect (DSA) for public schools, Department of Health Care Access and Information (HCAI) for hospitals, and Water Boards stormwater coverage at 1 acre or more.
- Schedule
- Quoted review time covers one round, not the permit date. Add corrections, rechecks, fees, and clearances.
Student Q&A
Questions students asked about K2, with answers from The Exit Club. All questions
Loading questions…
Something in K2 unclear? Log in to ask a question.
Log in to askYour questions
Sources & handbook wording
K2 · Knowledge of various agency impacts to project scopes and schedules.
- AIA B101–2017 ↗
§§3.1.3, 3.1.5–3.1.6, 4.2. §§5.1 and 5.3
- CAB CSE Handbook, April 2026 ↗
Domain 1, K2 and K6. PDF p.12