K2 — Project scope & schedule

Agencies control two things: what gets built and when. The exam divides the road to occupancy into three gates (planning, plan check, and inspection) and tests their order and realistic durations.

Three steps through the agenciesStep 01, entitlement, during SD and DD: 3 to 12 months small or medium, 6 to 24 large or complex. Step 02, plan check, during CD: 1 to 3 or 2 to 6 months, looping through comments and resubmittals until approved. Step 03, permit and construction, during CA: 6 to 12 or 6 to 24 months, with inspections at each stage, then final and the certificate of occupancy.Three steps through the agencies01EntitlementSD / DDSmall / medium3–12 moLarge / complex6–24 moUse and design allowed?02Plan checkCDSmall / medium1–3 moLarge / complex2–6 moCodes met?03Permit + buildCASmall / medium6–12 moLarge / complex6–24 moBuilt right, stage by stage?comments → fix → resubmituntil approvedInspections at each stage,then final and the C of OThree steps through the agenciesStep 01, entitlement, during SD and DD: 3 to 12 months small or medium, 6 to 24 large or complex. Step 02, plan check, during CD: 1 to 3 or 2 to 6 months, looping through comments and resubmittals until approved. Step 03, permit and construction, during CA: 6 to 12 or 6 to 24 months, with inspections at each stage, then final and the certificate of occupancy.Three steps throughthe agencies01EntitlementSD / DDSmall / medium3–12 moLarge / complex6–24 moUse and design allowed?02Plan checkCDSmall / medium1–3 moLarge / complex2–6 moCodes met?03Permit + buildCASmall / medium6–12 moLarge / complex6–24 moBuilt right, stage by stage?Plan check loops: comments,fix, resubmit, until approved.
Question

A theater conversion needs a use permit that could change its hours and access. Will a fully detailed construction set guarantee the approval?

01 / Entitlement approval

An entitlement is planning permission for a use or development, like a conditional use permit (K19). Handle it during schematic design (SD) and design development (DD): never sink money into construction documents before Planning says yes, since it can still reshape the size, layout, parking count, or hours of operation.

  • 3–12 months for small or medium projects, and 6–24 months for large or complex ones.
  • Environmental review, vocal neighbors, continued hearings, and appeals push you straight toward the long end.

02 / Plan check and agency review

Once entitled, the team draws construction documents (CD), packing the Energy Code forms (K37) and CALGreen checklist (K28) right inside. Building, Planning, Fire, and Public Works check the set against both the codes and your conditions of approval.

  • 1–3 months for small or medium projects, and 2–6 months for large or complex ones.

Plan check is a loop, not a line: collect comments, fix every sheet they touch, file a resubmittal, and usually go around again. One fire-access comment moving a driveway ripples across site, civil, and landscape sheets. Catch every ripple before resubmitting, or plan check happily invites you back for another round.

Question

The required inspection hasn’t happened yet. Does the permit holder have to give safe access and leave the work visible until it does?

03 / Building permit and construction

The building permit comes before the work it covers, followed by the building department's own inspections.

  • 6–12 months for small or medium projects, and 6–24 months for large or complex ones.
  • The building official must approve work to date before the contractor goes any further.
  • The permit holder provides safe access and leaves work exposed until approved: rebar and under-slab pipes before concrete, rough plumbing and electrical before drywall.
  • An architect's site visit never substitutes for a building inspection.

Final inspection and occupancy

After final inspection, the building official issues the Certificate of Occupancy to the owner. The architect's certificate of substantial completion is a contract document and never replaces it (K41): one settles the contract between the parties, while the other lets real people walk inside. Alterations keeping the existing legal occupancy may close out with just a final permit sign-off.

How agencies change the scope

Agency How it can change the project
Planning Conditions of approval on height, setbacks, parking, landscaping, materials, or hours
Environmental review Mitigation like sound walls, habitat buffers, or traffic improvements
Fire Access roads, truck turnarounds, hydrants, sprinklers, and alarms
Public Works Street and sidewalk improvements, right-of-way dedications, stormwater treatment
Utilities Transformer and meter locations, service upgrades, easements
Health Kitchen, pool, or medical layouts and finishes

Conditions of approval aren't hearing-night suggestions: they stay in your drawings until Planning formally agrees to change them.

State and regional reviews

Spot these at kickoff, before they ambush your schedule at permit time (K6).

Review When it applies Schedule effect
California Environmental Quality Act (CEQA) Discretionary approvals of non-exempt projects Often the longest stretch of entitlement
Coastal development permit Development in the coastal zone Before the building permit
Division of the State Architect (DSA) Public K–12 schools and community colleges Replaces the local building department. No construction until DSA approves in writing.
Department of Health Care Access and Information (HCAI) Hospitals and some other health facilities Handles both plan review and inspection
Water Boards Construction disturbing 1 acre or more Construction General Permit coverage and stormwater plan before grading
County health department Restaurants, markets, pools Plan approval before construction

Discretionary approvals (CEQA, coastal permits, entitlements) always precede ministerial plan check and the building permit. Asked what comes first? Pick the discretionary gate (K42).

Question

The building department quotes four weeks for plan check. Should the schedule show the permit four weeks after submittal?

Time allowances in the architect’s schedule

  • Under the American Institute of Architects (AIA) B101, your schedule budgets for owner decisions, consultant work, and agency review, not just drafting.
  • A dependency is work stuck waiting on an earlier step: pick kitchen equipment late, and engineering plus everything downstream slides.
  • A quoted review window covers one review, never the permit date. Four weeks of review, two of corrections, and three of recheck already total nine weeks, before fees or utility clearances. The review time isn't the permit date.

K2 / Quick check

Quiz

11 questions
← Quiz list
Question 1 of 11Choose one answer
A new medical clinic requires a conditional use permit. During which phases of design should the entitlement normally be obtained?

TLDR  ·  Quick Reference

Entitlement
Runs during schematic design and design development, before construction documents. 3–12 months (small/medium) or 6–24 months (large/complex).
Plan check
A loop of comments, coordinated fixes, and resubmittals. 1–3 months (small/medium) or 2–6 months (large/complex).
Construction
6–12 months (small/medium) or 6–24 months (large/complex). Work stops at each inspection until the building official approves it.
Occupancy
The building official issues the Certificate of Occupancy to the owner. Substantial completion never replaces it.
Scope impacts
Conditions of approval, environmental mitigation, fire access, Public Works improvements, health layouts, and utility easements can all reshape the design.
Order
Discretionary approvals like California Environmental Quality Act (CEQA) review and coastal permits precede ministerial plan check and the building permit.
State reviews
Division of the State Architect (DSA) for public schools, Department of Health Care Access and Information (HCAI) for hospitals, and Water Boards stormwater coverage at 1 acre or more.
Schedule
Quoted review time covers one round, not the permit date. Add corrections, rechecks, fees, and clearances.

Student Q&A

Questions students asked about K2, with answers from The Exit Club. All questions

Loading questions…

Sources & handbook wording

K2 · Knowledge of various agency impacts to project scopes and schedules.

  1. AIA B101–2017 ↗

    §§3.1.3, 3.1.5–3.1.6, 4.2. §§5.1 and 5.3

  2. CAB CSE Handbook, April 2026 ↗

    Domain 1, K2 and K6. PDF p.12